214 ppt 9 Soundness Testing and commissioning
Authored by Trevor Armstrong
Construction
11th Grade
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which type of joints should be checked to ensure they are tight before soundness testing?
Soldered joints
Compression joints
Welded joints
Glued joints
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be checked to ensure that soldered joints are properly made?
They are painted
They are insulated
They are visible
They are secure
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be attached after the system stands for 30 minutes?
Pressure gauge
Hydraulic test bucket
Water pump
Leak detector
4.
MULTIPLE CHOICE QUESTION
30 sec • 2 pts
What standard should the soundness testing conform to? (bonus point for correct answer)
BSEN800
BSEN806
BSEN810
BSEN820
5.
FILL IN THE BLANK QUESTION
30 sec • 1 pt
If the example pressure given for a system is working at 3 bar, the pressure we should test to is _____
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which material would be pressurised for an hour at 1.5x working pressure, to be assessed for soundness ?
Plastic pipes
Copper and steel pipes
Aluminum pipes
PVC pipes
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the first step in the soundness testing of a plastic pipe (polybutylene)?
Pump the system to 1 bar.
Walk around the system and check for leaks.
Slowly fill the system with water.
Increase pressure to 1.5 x working pressure.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?