Pc12 - Week 3
Authored by Tom Robinson
Construction
12th Grade
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
16 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the formula for calculating productivity?
Planned Output x Labour Hours
Planned Output / Labour Hours
Labour Hours / Planned Output
Labour Hours x Planned Output
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does a Productivity Index (PI) greater than 1 indicate?
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In project control, what does PI = 1 mean?
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If a crew of 5 workers works 8-hour days for 10 days, how many total work hours are available?
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
How is production different from productivity?
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which is a controllable factor affecting construction productivity?
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does PERT stand for?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?