A201 Contract Quiz

A201 Contract Quiz

University

11 Qs

quiz-placeholder

Similar activities

SITE VISIT QUIZ

SITE VISIT QUIZ

University

10 Qs

L: SET 0

L: SET 0

University - Professional Development

10 Qs

Professional Practice Quiz#3

Professional Practice Quiz#3

University

10 Qs

W: SET 2

W: SET 2

University

10 Qs

PD 1096

PD 1096

University

15 Qs

BLDG LAWS PD1096

BLDG LAWS PD1096

University

15 Qs

L: SET 1

L: SET 1

University

10 Qs

Architecture

Architecture

University

10 Qs

A201 Contract Quiz

A201 Contract Quiz

Assessment

Quiz

Architecture

University

Hard

Created by

AIAS University of Southern California

Used 1+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

When a contractor submits a “Contractor’s Application for Payment,” to the architect, how long does the architect have to formally issue to the Owner a “Certificate for Payment” or to notify the contractor and the owner of the architects’ reason for withholding certification?

7 days

14 days

One month

One pay cycle

2.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

Which of the following is NOT a valid reason for the architect withholding certification of payment?

A. defective Work not remedied

B. third party claims filed or reasonable evidence indicating probable filing of such claims, unless security acceptable to the Owner is provided by the Contractor

C. the payment request includes the cost of materials for construction that are stored off-site

D. failure of the Contractor to make payments properly to Subcontractors or suppliers for labor, materials or equipment

3.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

Which of the following is NOT a valid reason for the architect withholding certification of payment?

A. reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum

B. the architect was too busy working on their studio project to complete the assignment

C. reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay

D. repeated failure to carry out the Work in accordance with the Contract Documents.

4.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

The contractor shall take reasonable precautions for the safety and protect of each of these EXCEPT:

A. Employees on the Work and other persons who may be affected

B. The Work, materials, and equipment

C. Utilities designated for removal or replacement

D. Other property at the site or adjacent (such as trees, sidewalks, etc.)

5.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

After injury to a person or damage to property by any party, notice must be made to other party within:

A. One calendar day

B. 24 hours from the time of the incident

C. One week

D. 21 days

6.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

Who pays for the costs of remediation for failure to comply with requirements regarding hazardous materials and substances?

A. Contractor

B. Owner

C. Both contractor and owner equally

D. The contractor unless the remediation is due to the owner’s fault or negligence

7.

MULTIPLE CHOICE QUESTION

20 sec • 5 pts

Which party (or parties) shall be included on the Contractor’s commercial general liability insurance policy?

A. Owner

B. Owner and Architect

C. Owner and Architect and Architect’s Consultants

D. None of the above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?