PMP MCQ Series-Schedule

PMP MCQ Series-Schedule

Assessment

Quiz

Other

University

Medium

Created by

Shamsil ARFEEN

Used 1+ times

FREE Resource

Student preview

quiz-placeholder

38 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

1. A project manager is informed midway through Project Planning that she was given inaccurate data regarding,new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she can still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
A. Critical path method
B. Flowchart
C. Precedence diagramming
D. Work breakdown structure

Answer explanation

Explanation There are only two choices related to schedulings critical path method and precedence#diagramming Precedence diagramming is a diagramming technique that deals with the relationship between activities, not schedule flexibility. The project manager is analyzing the critical path.

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

2. A design engineer is helping to ensure that the dependencies within her area of expertise are properly defined,on the project. The design of several deliverables must be complete before manufacturing can begin. This is an example of what type of dependency?
A. Discretionary dependency
B. External dependency
C. Mandatory dependency
D. Scope dependency

Answer explanation

Explanation No mention is made that the dependency comes from a source outside the project, so this is#not an external dependency. Scope dependency is not a defined term. The key words in the question are "must be complete." Since the dependency is required, it could not be discretionary and therefore must be mandatory. The question defines a mandatory dependency

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

3. Your sponsor and stakeholders have made it clear they wish to be kept informed on the project status. There are,many aspects of the project on which you will report, and you want to choose the most appropriate tool to use in each case. Which of the following are generally illustrated better by bar charts than network diagrams?
A. Logical relationships
B. Critical paths
C. Resource trade-offs
D. Progress or status

Answer explanation

Explanation The bar chart is designed to show a relationship to time. This is best used when#demonstrating progress or status as a factor of time.

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

4. A heuristic is best described as a ;
A. Control tool
B. Scheduling method
C. Planning tool
D. Generally Accepted rule

Answer explanation

Explanation A heuristic is a generally accepted rule. Examples are cost per line of code and cost per#square foot of floor space. Explanation Total float and free float are the time an activity can be delayed without impacting the

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

5. Lag means:
A. The amount of time an activity can be delayed without delaying the project finish date
B. The amount of time an activity can be delayed without delaying the early start date of its successor
C. Waiting time
D. The product of a forward and backward pass

Answer explanation

entire project or the next activity. A forward or backward pass refers to a network analysis technique,#not waiting time. Waiting time is the correct definition of lag.

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

6. A project manager is new to the company but has 10 years of project management experience. She is given a,medium-sized project and is asked to plan so it is finished as quickly as possible because the company has a large list of projects to complete in the coming year. She will be given another project to manage as soon as she has this one baselined. She needs to report on the longest time the project will take. Which of the following is the best project management tool to use to determine this?
A. Work breakdown structure
B. Network diagram
C. Bar chart
D. Project charter

Answer explanation

Explanation The bar chart may show an end date, but it is not used to determine dates. The project#charter also may include a required end date but not a logical determination of how long the project will take. The network diagram shows dependencies between activities on the project activity list. The dependencies allow us to look at the various paths through the diagram to determine the longest duration (critical) path. The network diagram is the best answer.

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

7. Which of the following is correct?
A. The critical path helps prove how long the project will take.
B. There can be only one critical path.
C. The network diagram will change every time the end date changes.
D. A project can never have negative float.

Answer explanation

Explanation This question tests your knowledge about a number of topics. There can often be more than#one critical path, but you might adjust the plan in order to decrease risk and have only one critical path. The network diagram may or may not change when the end date changes, depending on the amount of schedule reserve and the reason for the change to the schedule. You can have negative float if you are behind schedule. The critical path helps prove how long the project will take. This is the only correct statement of the choices given.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?