
Disruption Claims in Construction Projects

Quiz
•
Business
•
University
•
Hard
Prashanth Sreram
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the primary purpose of a disruption claim in a construction project?
To request additional time for project completion
To claim compensation for changes in scope
To request reimbursement for increased project costs due to delays
To claim damages for harm caused by workers
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is typically required to support a disruption claim in a construction project?
Proof of loss of profit
A detailed analysis of the delay or disruption
A letter from the project owner
Proof of contractor's negligence
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of these could be considered a cause for a disruption claim in a construction project?
Contractor's failure to meet project milestones
Unexpected site conditions or delays caused by the client
Minor weather delays that do not impact the project timeline
Subcontractor errors not impacting overall project progress
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a common method used to calculate the cost of disruption in a construction claim?
Time and materials calculation
Cost per square foot of the project
Evaluation of labor inefficiencies and equipment delays
Lump-sum estimation of the entire project
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When should a disruption claim ideally be submitted?
Only at the end of the project
As soon as the disruption is recognized
At the time of contract signing
After all work is completed
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In the context of a disruption claim, 'acceleration' refers to:
The project's progress meeting the planned schedule
A request for additional time to complete work
A situation where the contractor is forced to speed up work due to disruptions
An increase in labor and material costs due to project delays
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following documents can help substantiate a disruption claim?
Change orders
Daily logs or reports from the contractor
Communications between the contractor and the client
All of the above
Create a free account and access millions of resources
Similar Resources on Wayground
14 questions
Project Budgeting and Resource Allocation

Quiz
•
University
12 questions
Together Towards Tomorrow

Quiz
•
University
11 questions
Modal Perfect Quiz

Quiz
•
University
18 questions
Causes of Construction Claims

Quiz
•
University
18 questions
Acceleration Claims in Construction

Quiz
•
University
16 questions
Construction Claims Quiz

Quiz
•
University
20 questions
0MEH-Unit 1: Overview and Framework (EN)

Quiz
•
University
10 questions
0MEH-Unit 1 Overview and Framework. Overview (EN)

Quiz
•
University
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade