Search Header Logo

Disruption Claims in Construction Projects

Authored by Prashanth Sreram

Business

University

Disruption Claims in Construction Projects
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the primary purpose of a disruption claim in a construction project?

To request additional time for project completion

To claim compensation for changes in scope

To request reimbursement for increased project costs due to delays

To claim damages for harm caused by workers

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is typically required to support a disruption claim in a construction project?

Proof of loss of profit

A detailed analysis of the delay or disruption

A letter from the project owner

Proof of contractor's negligence

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of these could be considered a cause for a disruption claim in a construction project?

Contractor's failure to meet project milestones

Unexpected site conditions or delays caused by the client

Minor weather delays that do not impact the project timeline

Subcontractor errors not impacting overall project progress

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is a common method used to calculate the cost of disruption in a construction claim?

Time and materials calculation

Cost per square foot of the project

Evaluation of labor inefficiencies and equipment delays

Lump-sum estimation of the entire project

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When should a disruption claim ideally be submitted?

Only at the end of the project

As soon as the disruption is recognized

At the time of contract signing

After all work is completed

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In the context of a disruption claim, 'acceleration' refers to:

The project's progress meeting the planned schedule

A request for additional time to complete work

A situation where the contractor is forced to speed up work due to disruptions

An increase in labor and material costs due to project delays

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following documents can help substantiate a disruption claim?

Change orders

Daily logs or reports from the contractor

Communications between the contractor and the client

All of the above

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?