Disruption Claims in Construction Projects

Disruption Claims in Construction Projects

University

15 Qs

quiz-placeholder

Similar activities

Business Communication Chapter 8 Assessment

Business Communication Chapter 8 Assessment

9th Grade - University

14 Qs

Causes of Construction Claims

Causes of Construction Claims

University

18 Qs

Construction Claims Quiz

Construction Claims Quiz

University

16 Qs

PM - Chapter 5

PM - Chapter 5

University

18 Qs

0MEH-Unit 1: Overview and Framework (EN)

0MEH-Unit 1: Overview and Framework (EN)

University

20 Qs

Project Budgeting and Resource Allocation

Project Budgeting and Resource Allocation

University

14 Qs

Managing Project Scheduling

Managing Project Scheduling

University

20 Qs

Business Methodologies Quiz

Business Methodologies Quiz

University

19 Qs

Disruption Claims in Construction Projects

Disruption Claims in Construction Projects

Assessment

Quiz

Business

University

Hard

Created by

Prashanth Sreram

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the primary purpose of a disruption claim in a construction project?

To request additional time for project completion

To claim compensation for changes in scope

To request reimbursement for increased project costs due to delays

To claim damages for harm caused by workers

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is typically required to support a disruption claim in a construction project?

Proof of loss of profit

A detailed analysis of the delay or disruption

A letter from the project owner

Proof of contractor's negligence

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of these could be considered a cause for a disruption claim in a construction project?

Contractor's failure to meet project milestones

Unexpected site conditions or delays caused by the client

Minor weather delays that do not impact the project timeline

Subcontractor errors not impacting overall project progress

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is a common method used to calculate the cost of disruption in a construction claim?

Time and materials calculation

Cost per square foot of the project

Evaluation of labor inefficiencies and equipment delays

Lump-sum estimation of the entire project

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When should a disruption claim ideally be submitted?

Only at the end of the project

As soon as the disruption is recognized

At the time of contract signing

After all work is completed

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In the context of a disruption claim, 'acceleration' refers to:

The project's progress meeting the planned schedule

A request for additional time to complete work

A situation where the contractor is forced to speed up work due to disruptions

An increase in labor and material costs due to project delays

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following documents can help substantiate a disruption claim?

Change orders

Daily logs or reports from the contractor

Communications between the contractor and the client

All of the above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Business