1.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project is approaching its project closure phase, and the project manager receives an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts. Which three actions should the project manager ask the project specialist to take? (Choose three)
2.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project. What are the first two actions the project manager should perform? (Choose two)
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project manager is assigned to a time-bound internal project on quality improvement. During project execution the project manager observes that a specific team member is being isolated by other team members. Which three actions should the project manager take? (Choose three)
4.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals. What two options will help the team initially address this obstacle? (Choose two)
5.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project manager is assigned to a project that is in development. As the project manager reviews the project's progress, they find a few tasks that are behind schedule. After investigating, the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager's project. Which two actions can the project manager take to bring the team back on track? (Choose two)
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Due to a recent budget reduction, two team members were released from an agile team. The customer is still expecting early results for the project. Which two actions should the project manager take to align customer expectations? (Choose two)
7.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project manager is leading a meeting with key stakeholders, the project sponsor, and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed. Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
14 questions
Line Crew Leadership and Practices Quiz
Quiz
•
Professional Development
10 questions
Untitled Quizs
Quiz
•
Professional Development
10 questions
Preguntas sobre Construcción
Quiz
•
Professional Development
9 questions
Quiz on Atomic Structure and Forces
Quiz
•
Professional Development
10 questions
October Sales Meeting Quiz
Quiz
•
Professional Development
10 questions
Power Delivery System Quiz
Quiz
•
Professional Development
15 questions
Quiz on Combustion and CO Detectors
Quiz
•
Professional Development
14 questions
Grounding and Electrical Safety Quiz
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade
Discover more resources for Construction
10 questions
How to Email your Teacher
Quiz
•
Professional Development
6 questions
3RD GRADE DECLARATION OF INDEPENDENCE EXIT TICKET
Quiz
•
Professional Development
19 questions
Black History Month Trivia
Quiz
•
6th Grade - Professio...
22 questions
Multiplying Exponents with the Same Base
Quiz
•
9th Grade - Professio...
40 questions
Flags of the World
Quiz
•
KG - Professional Dev...