Program Strategy Alignment

Quiz
•
Professional Development
•
1st Grade
•
Easy
Purwedi Darminto
Used 2+ times
FREE Resource
23 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After you had been assigned to manage an important program in your organization, one stakeholder objected to initiate the program until the program feasibility study is developed. Which of the following is not considered a reason for the organization to have a feasibility study?
Ensure a program's alignment with the vision, organizational strategy, and objectives
Clarify and define program requirements and risks
Clarify and define the program milestones
Clarify and define program objectives
Answer explanation
Options (A), (B), and (D) are considered reasons for the organization to have a feasibility study, but option (C) is not. Therefore, the right answer is an option (C).
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The senior management in your organization is trying to identify the total sum of all tangible & intangible elements that exixt in the organization. To ease this process, they requested all the project & program managers to provide the necessary supporting information. What is the likely outcome of this?
Identify the business value
Identify the future goals
Identify the business needs
Part of project & program monitoring process
Answer explanation
Business value may be defined as the sum of all tangible and intangible elements of a business where, for example, tangible elements include monetary assets, facilities, fixtures, equity, tools, market share, and utility. Intangible elements may include goodwill, brand recognition, public benefit, trademarks, compliance, reputation, strategic alignment, and capabilities. The business value may also be created through the effective management of ongoing well-established operations.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who provides the necessary support to the program manager to support program-level change management activities?
Component project managers
Program management team
Program Management office
Senior Management
Answer explanation
A program management office is an important element of the program's infrastructure and an aid to the program manager. It may support the program manager with the management of supporting program-level change management activities.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A manufacturer of luxury automobiles is keen on entering into a new market, which seems to have much potential. What should be the first step for the company on this venture?
Establish a joint venture with a local automobile company that has a better understanding of the local market and local regulations
Prepare a business case to understand the implications of this venture for the overall organization
Undertake a detailed market study to figure out the demand for luxury automobiles in the target market
Issue a program charter and appoint a program manager who is a resident of the target market region and an expert in the automobile industry
Answer explanation
Option B is correct. The first step should be to prepare a business case and come up with a business justification. The market study may be a part of the business case preparation activity, but not necessarily so. If there is already data available about the target market, then market research may not be required. Also, establishing a joint venture may or may not be desirable and seems a bit presumptive when the program is still in the evaluation stage. For a similar reason, the issuance of a program charter is a little premature. The business justification need to be created first.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which statement below is TRUE?
Project Management drives Organizational strategies
Program Management drives Organizational strategies
Organizational strategies drive Project, Program & Portfolio management
Organizational strategies drive only Portfolio management and not Project, Program management
Answer explanation
Option C is the correct statement.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You need to initiate a program. As a program manager, you document how the projects and other program components configured to deliver the program and the intended benefits. Which program artifact are you preparing?
Business Case
Program Roadmap
Benefits management plan
Program Charter
Answer explanation
Directly mapped question to standard; please refer to section 7.1.2.1 on Page # 93.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A program manager uses a graph to present senior management about the program's key milestones and decision points where senior management involvement is needed. Which document program manager is using for this presentation?
Program charter
Program roadmap
Benefits management plan
Program Management Plan
Answer explanation
The program roadmap is a chronological representation of a program's intended direction, graphically depicting dependencies between major milestones and decision points, reflecting the linkage between the business strategy and the program work.
Create a free account and access millions of resources
Similar Resources on Wayground
22 questions
PMI SH - Engage Stakeholders and Build Shared Understanding

Quiz
•
1st Grade
19 questions
Quality Induction Quiz

Quiz
•
1st Grade
22 questions
Microsoft 98-365 Server Admin Part 2

Quiz
•
KG - Professional Dev...
20 questions
Service Management Training - Quiz

Quiz
•
KG - Professional Dev...
20 questions
TKTmodule1

Quiz
•
1st - 4th Grade
18 questions
PMI SH - Evaluate and Deliver Project Benefits and Value

Quiz
•
1st Grade
24 questions
PMI SH - Evaluate and Address External Business Environment Chan

Quiz
•
1st - 3rd Grade
20 questions
Day#3 ISO 27001 Lead Auditor

Quiz
•
1st Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade