Before the project begins, who determines the scope, schedule & cost?

Project Manager

Project Sponsor

Project Stakeholder

Project Team

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What are scope, schedule, and cost referred to as?

Iron Triangle

Iron Points

Contractions

Conjunctions

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

The business case is a project document.

True

False

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

Project A has an NPV of $5,000. Project B has an NPV of $10,000. Which project would you do?

Project A

Project B

Either

Neither

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

You are assessing a project proposal for a project that will run over many years, involving costs and benefits over the entire timeline. Which tool should you use to assess the project's finances?

Balanced Score Card

Weighted Scoring Model

Net Present Value

Net Future Value

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

Project C has an ROI of 4%, payback of 3 years. Project D has an ROI of 3%, payback of 2 years. Which project would you do?

Project C

Project D

Neither

Either

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

How many process groups are there?

10

6

5

3

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?