What is the primary purpose of the critical path in project scheduling?
Quiz Lesson 3 - Topic C (Schedule)

Quiz
•
Professional Development
•
Professional Development
•
Hard
Abdul Habib Aulfat
Used 4+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To identify tasks that can be delayed without impacting the project completion date
To determine the longest sequence of activities with the shortest project duration
To visualize task dependencies and relationships in a Gantt chart
To calculate the total float of all project activities
Answer explanation
The primary purpose of the critical path is to determine the longest sequence of activities that dictates the shortest project duration, ensuring timely project completion.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which estimating technique uses a weighted average that gives more emphasis to the most likely duration?
Analogous estimating
Parametric estimating
Three-point estimating (PERT)
Bottom-up estimating
Answer explanation
Three-point estimating (PERT) uses a weighted average of three estimates: optimistic, pessimistic, and most likely. This technique emphasizes the most likely duration, making it the correct choice for the question.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a precedence diagramming method (PDM), which type of dependency is considered mandatory?
External dependency
Soft logic dependency
Hard logic dependency
Discretionary dependency
Answer explanation
In PDM, a hard logic dependency is mandatory because it is based on the inherent nature of the work. It cannot be changed or ignored, unlike discretionary or soft logic dependencies, which are more flexible.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does 'float' in project scheduling represent?
The amount of time a task can be delayed without impacting the project’s overall completion date
The slack time available between activities on the critical path
The actual duration of an activity including non-working days
The difference between early finish and late start dates
Answer explanation
'Float' represents the amount of time a task can be delayed without affecting the project's overall completion date. This allows for flexibility in scheduling without jeopardizing deadlines.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which schedule compression technique involves overlapping phases or tasks to save time?
Resource leveling
Crashing
Fast-tracking
Resource smoothing
Answer explanation
Fast-tracking is a schedule compression technique that involves overlapping phases or tasks to save time, making it the correct choice for this question.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the first step when using a bottom-up estimating technique?
Analyzing historical data for similar projects
Aggregating estimates for individual tasks
Decomposing work packages into activities
Determining the weighted average for task durations
Answer explanation
The first step in bottom-up estimating is decomposing work packages into activities. This allows for detailed estimation of each task, leading to more accurate overall project estimates.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What tool is preferred for visually mapping critical paths and dependencies in predictive projects?
Gantt chart
Precedence Diagramming Method (PDM)
Milestone chart
Kanban board
Answer explanation
The Precedence Diagramming Method (PDM) is preferred for visually mapping critical paths and dependencies in predictive projects, as it clearly illustrates task relationships and sequencing.
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Proj Integration Management

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
10 questions
Mentoring & Coaching Pertemuan 6 Schedule and Cost POST TEST

Quiz
•
Professional Development
7 questions
Schedule Final Quiz - Assignment

Quiz
•
Professional Development
10 questions
PROJECT RISK MANAGEMENT

Quiz
•
Professional Development
10 questions
CGEIT Domain 2 MCQ (Additional)

Quiz
•
Professional Development
12 questions
504

Quiz
•
Professional Development
10 questions
Project Scope Management

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade