Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Professional Development

10 Qs

quiz-placeholder

Similar activities

Pre and Post Test

Pre and Post Test

Professional Development

10 Qs

Pre & Post Test QCC

Pre & Post Test QCC

Professional Development

10 Qs

Microsoft 365

Microsoft 365

Professional Development

11 Qs

SLS PS 2.0 Types of Learning Experiences (LE)

SLS PS 2.0 Types of Learning Experiences (LE)

Professional Development

10 Qs

Pivot Tables

Pivot Tables

Professional Development

10 Qs

Design Basics of Substation  engineering

Design Basics of Substation engineering

Professional Development

10 Qs

Soal PPPK Pedagogik 4

Soal PPPK Pedagogik 4

Professional Development

15 Qs

Trg@home 1

Trg@home 1

Professional Development

10 Qs

Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Hard

Created by

Abdul Habib Aulfat

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the critical path in project scheduling?

To identify tasks that can be delayed without impacting the project completion date

To determine the longest sequence of activities with the shortest project duration

To visualize task dependencies and relationships in a Gantt chart

To calculate the total float of all project activities

Answer explanation

The primary purpose of the critical path is to determine the longest sequence of activities that dictates the shortest project duration, ensuring timely project completion.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which estimating technique uses a weighted average that gives more emphasis to the most likely duration?

Analogous estimating

Parametric estimating

Three-point estimating (PERT)

Bottom-up estimating

Answer explanation

Three-point estimating (PERT) uses a weighted average of three estimates: optimistic, pessimistic, and most likely. This technique emphasizes the most likely duration, making it the correct choice for the question.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a precedence diagramming method (PDM), which type of dependency is considered mandatory?

External dependency

Soft logic dependency

Hard logic dependency

Discretionary dependency

Answer explanation

In PDM, a hard logic dependency is mandatory because it is based on the inherent nature of the work. It cannot be changed or ignored, unlike discretionary or soft logic dependencies, which are more flexible.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does 'float' in project scheduling represent?

The amount of time a task can be delayed without impacting the project’s overall completion date

The slack time available between activities on the critical path

The actual duration of an activity including non-working days

The difference between early finish and late start dates

Answer explanation

'Float' represents the amount of time a task can be delayed without affecting the project's overall completion date. This allows for flexibility in scheduling without jeopardizing deadlines.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which schedule compression technique involves overlapping phases or tasks to save time?

Resource leveling

Crashing

Fast-tracking

Resource smoothing

Answer explanation

Fast-tracking is a schedule compression technique that involves overlapping phases or tasks to save time, making it the correct choice for this question.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step when using a bottom-up estimating technique?

Analyzing historical data for similar projects

Aggregating estimates for individual tasks

Decomposing work packages into activities

Determining the weighted average for task durations

Answer explanation

The first step in bottom-up estimating is decomposing work packages into activities. This allows for detailed estimation of each task, leading to more accurate overall project estimates.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What tool is preferred for visually mapping critical paths and dependencies in predictive projects?

Gantt chart

Precedence Diagramming Method (PDM)

Milestone chart

Kanban board

Answer explanation

The Precedence Diagramming Method (PDM) is preferred for visually mapping critical paths and dependencies in predictive projects, as it clearly illustrates task relationships and sequencing.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?