Quiz Lesson 3 - Topic C (Schedule)

Quiz
•
Professional Development
•
Professional Development
•
Hard
Abdul Habib Aulfat
Used 4+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of the critical path in project scheduling?
To identify tasks that can be delayed without impacting the project completion date
To determine the longest sequence of activities with the shortest project duration
To visualize task dependencies and relationships in a Gantt chart
To calculate the total float of all project activities
Answer explanation
The primary purpose of the critical path is to determine the longest sequence of activities that dictates the shortest project duration, ensuring timely project completion.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which estimating technique uses a weighted average that gives more emphasis to the most likely duration?
Analogous estimating
Parametric estimating
Three-point estimating (PERT)
Bottom-up estimating
Answer explanation
Three-point estimating (PERT) uses a weighted average of three estimates: optimistic, pessimistic, and most likely. This technique emphasizes the most likely duration, making it the correct choice for the question.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a precedence diagramming method (PDM), which type of dependency is considered mandatory?
External dependency
Soft logic dependency
Hard logic dependency
Discretionary dependency
Answer explanation
In PDM, a hard logic dependency is mandatory because it is based on the inherent nature of the work. It cannot be changed or ignored, unlike discretionary or soft logic dependencies, which are more flexible.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does 'float' in project scheduling represent?
The amount of time a task can be delayed without impacting the project’s overall completion date
The slack time available between activities on the critical path
The actual duration of an activity including non-working days
The difference between early finish and late start dates
Answer explanation
'Float' represents the amount of time a task can be delayed without affecting the project's overall completion date. This allows for flexibility in scheduling without jeopardizing deadlines.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which schedule compression technique involves overlapping phases or tasks to save time?
Resource leveling
Crashing
Fast-tracking
Resource smoothing
Answer explanation
Fast-tracking is a schedule compression technique that involves overlapping phases or tasks to save time, making it the correct choice for this question.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the first step when using a bottom-up estimating technique?
Analyzing historical data for similar projects
Aggregating estimates for individual tasks
Decomposing work packages into activities
Determining the weighted average for task durations
Answer explanation
The first step in bottom-up estimating is decomposing work packages into activities. This allows for detailed estimation of each task, leading to more accurate overall project estimates.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What tool is preferred for visually mapping critical paths and dependencies in predictive projects?
Gantt chart
Precedence Diagramming Method (PDM)
Milestone chart
Kanban board
Answer explanation
The Precedence Diagramming Method (PDM) is preferred for visually mapping critical paths and dependencies in predictive projects, as it clearly illustrates task relationships and sequencing.
Create a free account and access millions of resources
Similar Resources on Wayground
12 questions
504

Quiz
•
Professional Development
7 questions
Planning for Success Part 2

Quiz
•
Professional Development
15 questions
Alestra Diagnóstico

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Quiz
•
Professional Development
10 questions
PROJECT RISK MANAGEMENT

Quiz
•
Professional Development
6 questions
Feasibility Estimating

Quiz
•
Professional Development
12 questions
UPIP PMP-Scheduling-Cost-quality

Quiz
•
Professional Development
15 questions
Nodejs: Packages and Package.json

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade