Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Professional Development

10 Qs

quiz-placeholder

Similar activities

Schedule Management AC-2019

Schedule Management AC-2019

Professional Development

10 Qs

Schedule Management Terms - Assignment

Schedule Management Terms - Assignment

Professional Development

7 Qs

Project Management Master Class 3

Project Management Master Class 3

Professional Development

10 Qs

SG20_Test_S5_CH6 Schedule

SG20_Test_S5_CH6 Schedule

Professional Development

10 Qs

Pre-Test

Pre-Test

Professional Development

11 Qs

Project Management

Project Management

Professional Development

15 Qs

Atoha lesson 7

Atoha lesson 7

Professional Development

12 Qs

CAPM 1 (10 Questions)

CAPM 1 (10 Questions)

Professional Development

10 Qs

Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Abdul Habib Aulfat

Used 4+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the critical path in project scheduling?

To identify tasks that can be delayed without impacting the project completion date

To determine the longest sequence of activities with the shortest project duration

To visualize task dependencies and relationships in a Gantt chart

To calculate the total float of all project activities

Answer explanation

The primary purpose of the critical path is to determine the longest sequence of activities that dictates the shortest project duration, ensuring timely project completion.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which estimating technique uses a weighted average that gives more emphasis to the most likely duration?

Analogous estimating

Parametric estimating

Three-point estimating (PERT)

Bottom-up estimating

Answer explanation

Three-point estimating (PERT) uses a weighted average of three estimates: optimistic, pessimistic, and most likely. This technique emphasizes the most likely duration, making it the correct choice for the question.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a precedence diagramming method (PDM), which type of dependency is considered mandatory?

External dependency

Soft logic dependency

Hard logic dependency

Discretionary dependency

Answer explanation

In PDM, a hard logic dependency is mandatory because it is based on the inherent nature of the work. It cannot be changed or ignored, unlike discretionary or soft logic dependencies, which are more flexible.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does 'float' in project scheduling represent?

The amount of time a task can be delayed without impacting the project’s overall completion date

The slack time available between activities on the critical path

The actual duration of an activity including non-working days

The difference between early finish and late start dates

Answer explanation

'Float' represents the amount of time a task can be delayed without affecting the project's overall completion date. This allows for flexibility in scheduling without jeopardizing deadlines.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which schedule compression technique involves overlapping phases or tasks to save time?

Resource leveling

Crashing

Fast-tracking

Resource smoothing

Answer explanation

Fast-tracking is a schedule compression technique that involves overlapping phases or tasks to save time, making it the correct choice for this question.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step when using a bottom-up estimating technique?

Analyzing historical data for similar projects

Aggregating estimates for individual tasks

Decomposing work packages into activities

Determining the weighted average for task durations

Answer explanation

The first step in bottom-up estimating is decomposing work packages into activities. This allows for detailed estimation of each task, leading to more accurate overall project estimates.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What tool is preferred for visually mapping critical paths and dependencies in predictive projects?

Gantt chart

Precedence Diagramming Method (PDM)

Milestone chart

Kanban board

Answer explanation

The Precedence Diagramming Method (PDM) is preferred for visually mapping critical paths and dependencies in predictive projects, as it clearly illustrates task relationships and sequencing.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?