Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
•
Professional Development
•
Medium
Abdul Habib Aulfat
Used 2+ times
FREE Resource
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What artifact is primarily used to determine the acceptance criteria in a predictive development approach?
Work breakdown structure
Scope statement
Project charter
Risk register
Answer explanation
The scope statement defines the project's deliverables and acceptance criteria, making it the primary artifact for determining what is included in the project. Other options do not specifically outline acceptance criteria.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an adaptive development approach, what helps determine the acceptance criteria for user stories?
Scope baseline
Definition of Done
Stakeholder register
Cost management plan
Answer explanation
The Definition of Done outlines the criteria that must be met for user stories to be considered complete, making it essential for determining acceptance criteria in an adaptive development approach.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which earned value management (EVM) measure is used to assess cost performance?
Schedule Performance Index (SPI)
Cost Performance Index (CPI)
Actual Cost (AC)
Planned Value (PV)
Answer explanation
The Cost Performance Index (CPI) measures cost efficiency by comparing earned value to actual costs. It indicates how well the project is staying within budget, making it the key EVM measure for assessing cost performance.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which tool would you use to visualize project work and monitor progress in an Agile environment?
Gantt chart
Burndown chart
Histogram
Pareto chart
Answer explanation
A burndown chart is specifically designed for Agile environments to visualize work completed versus work remaining over time, making it ideal for monitoring project progress.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of a Cumulative Flow Diagram in Kanban?
To measure financial expenditures
To track different stages of work items
To document project risks
To establish project scope
Answer explanation
A Cumulative Flow Diagram in Kanban is used to visualize and track the different stages of work items, helping teams understand workflow efficiency and identify bottlenecks.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does a project manager ensure that the scope is validated in an adaptive project environment?
By adhering strictly to the initial project plan
By customer acceptance of deliverables
By following a predetermined budget
By conducting weekly team meetings
Answer explanation
In an adaptive project environment, validating scope is achieved through customer acceptance of deliverables, ensuring that the project meets evolving requirements and stakeholder expectations.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which activity is essential when managing risks in a project?
Reducing the number of team meetings
Increasing the project budget
Monitoring and updating the risk register
Limiting scope changes
Answer explanation
Monitoring and updating the risk register is essential for managing risks in a project, as it helps identify new risks and track existing ones, ensuring proactive responses and informed decision-making.
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the role of performance reviews in project management?
To reassign team members to different tasks
To provide entertainment during project meetings
To analyze project performance and identify areas for improvement
To finalize the project budget
Answer explanation
Performance reviews are essential in project management as they help analyze project performance and identify areas for improvement, ensuring the project stays on track and meets its goals.
Similar Resources on Wayground
9 questions
Understand the situational context of projects

Quiz
•
Professional Development
10 questions
Scrum Stars

Quiz
•
Professional Development
7 questions
ID, PH & CN: L1 Fr#m#w#rk

Quiz
•
Professional Development
10 questions
INKALI - Performance Management System

Quiz
•
Professional Development
8 questions
Quiz Lesson 3 - Topic B (Scope)

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 3

Quiz
•
Professional Development
8 questions
PMC 2023 - The Importance of Planning in Project Mgmt

Quiz
•
Professional Development
10 questions
Atoha PMP lesson 14

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade