
CAPM Simulation Exam 1
Authored by Putri -
others

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
38 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(1) As part of a periodic risk review, the steering committee members express concern about a significant risk that the project team missed identifying while planning the previous sprint. At the following sprint planning meeting, the project manager and team devise an appropriate, cost-effective, and realistic response plan and assign a risk owner. What else should the project manager do?
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(2) A senior executive proposes starting a project to replace a significant portion of the company’s labor force with an automated production line. Other executives express skepticism about whether this approach is the best way to boost profit margins and question whether they are prepared to sponsor such an initiative. What should be the first step in this scenario?
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(3) You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle charges, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle. With the project life cycle selected, how will risk and cost be controlled?
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(4) You take over a project that has just been baselined. You review the project management plan and realize that while the development phase of the project will use an adaptive lifecycle, the development team does not have any experience with agile methodologies. The resource management plan does not specify any agile training. What should you do first?
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(5) A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints. The project manager has gathered the following information: - 17 story points were completed and accepted in the seventh sprint - 20 story points were planned for sprint #7 - One feature worth 3 story points was completed but rejected and placed back in the product backlog - The value of the features developed to date is $172,000 - Actual costs to date are $167,000 - The BAC for the project is $300,000 - The project backlog contains 250 story points - The project team has successfully completed 137 story points to date Which of the following accurately describes the schedule performance of the project for the seventh iteration?
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(6) Just after the daily scrum, the project sponsor stops by the war room and introduces a new member of the organization whose role will be impacted by the project. Now that a new stakeholder has been identified, what should the agile leader do next?
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
(7) The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics. At the retrospective, the team determines that the cost performance index (CPI) of the iteration was _______. (On the actual exam, you will be requested to fill in the blank with the letter representing the correct answer. But here in the simulator, please select the answer below.)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
33 questions
m3 repaso
Quiz
•
KG - University
40 questions
UD.02 Saneamiento
Quiz
•
Professional Development
39 questions
sử cuối kì
Quiz
•
9th - 12th Grade
36 questions
4th Grade Science: Part 1 Lessons 3-4
Quiz
•
KG - University
40 questions
Prova 11 - CFC
Quiz
•
KG - University
40 questions
Soal Bahasa Sunda Semester 1 Taun Ajaran 2023/2024
Quiz
•
KG - University
43 questions
SOAL PENYISIHAN LCC PORSEKA 2024
Quiz
•
1st - 5th Grade
42 questions
TRY OUT ASESMEN
Quiz
•
KG - University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for others
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade