Which project management methodology uses iterative development and prioritises adaptability?

RCE 12.2 tools

Quiz
•
Computers
•
12th Grade
•
Hard
Chris Keeble
Used 2+ times
FREE Resource
31 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Waterfall
Agile
Spiral
RAD
Answer explanation
The Agile methodology emphasizes iterative development and flexibility, allowing teams to adapt to changes quickly. Unlike Waterfall, which is linear, Agile focuses on continuous improvement and customer feedback.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which framework within Agile is based on visualising tasks on a board?
Scrum
Kanban
Lean
Spiral
Answer explanation
Kanban is an Agile framework that emphasizes visualizing tasks on a board, allowing teams to manage workflow and improve efficiency. Unlike Scrum, which uses sprints, Kanban focuses on continuous delivery.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a key feature of the Waterfall methodology?
Iterative development
Quick prototyping
Definitive stages that follow a sequence
Stakeholder involvement in each phase
Answer explanation
A key feature of the Waterfall methodology is its definitive stages that follow a sequence. This means each phase must be completed before moving to the next, contrasting with iterative or prototyping approaches.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which tool is used to track time scales and milestones?
Flowchart
Stakeholder matrix
Gantt chart
Budget sheet
Answer explanation
A Gantt chart is specifically designed to track time scales and milestones in project management, visually representing tasks along a timeline, making it the correct choice for this question.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which methodology focuses on continuous prototyping and user feedback?
Agile
Waterfall
RAD
Spiral
Answer explanation
RAD (Rapid Application Development) emphasizes continuous prototyping and user feedback, allowing for quick adjustments based on user input. This makes it distinct from methodologies like Waterfall and Agile.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a flowchart represent in project management?
Financial planning
Logical workflows or processes
Time scales and dependencies
Stakeholder influence
Answer explanation
A flowchart in project management visually represents logical workflows or processes, illustrating the sequence of steps and decisions involved in a project, making it easier to understand and communicate complex processes.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a common use for a stakeholder power-interest matrix?
Tracking project milestones
Identifying project risks
Prioritising stakeholders based on influence and interest
Answer explanation
A stakeholder power-interest matrix is used to prioritise stakeholders based on their influence and interest in a project, helping to manage their engagement effectively.
Create a free account and access millions of resources
Similar Resources on Quizizz
35 questions
EXAM PM PART 3 (72-106 QUESTIONS)

Quiz
•
12th Grade
35 questions
Waterfall Model Quiz

Quiz
•
12th Grade
26 questions
Metodologías de Desarrollo de Software

Quiz
•
12th Grade
31 questions
Sprawdzianik 2

Quiz
•
12th Grade - University
27 questions
T-Level Digital Infrastructure Core Units 1-10 revisit

Quiz
•
12th Grade
26 questions
Technology Quiz

Quiz
•
12th Grade
32 questions
Metodologías Ágiles en Desarrollo de Software

Quiz
•
12th Grade
30 questions
Ethical and Legal - Project Management

Quiz
•
12th Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade