Bai Tap PMP 5

Bai Tap PMP 5

University

70 Qs

quiz-placeholder

Similar activities

Parallel - FA1

Parallel - FA1

University

66 Qs

R va AT-2

R va AT-2

University

65 Qs

BPM e Governança de TI

BPM e Governança de TI

University

71 Qs

AWS Practice Questions Part 2

AWS Practice Questions Part 2

University

72 Qs

AWS Practice Questions Part 3

AWS Practice Questions Part 3

University

72 Qs

Module 9-12 exam

Module 9-12 exam

University

67 Qs

PROGRAMMING QUIZZES

PROGRAMMING QUIZZES

University

66 Qs

Networking and Security Quiz

Networking and Security Quiz

University

65 Qs

Bai Tap PMP 5

Bai Tap PMP 5

Assessment

Quiz

Information Technology (IT)

University

Easy

Created by

Bui Hoang

Used 5+ times

FREE Resource

70 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems.What should the project manager do next?
A. Apply the terms and conditions of the contract with penalties.
B. Issue a change request to reflect the anticipated date for training.
C. Help the customer find an alternative location to start the training.
D. Update the project schedule with the new date for training.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing emails, which contain useful information but are unmanageable due to the high volume.What should the project manager do to solve this problem?
A. Establish an unofficial communications method for the team to share knowledge and lessons learned.
B. Establish a pull communications method to access knowledge repositories and lessons learned.
C. Establish an interactive communications method between stakeholders to share knowledge and lessons learned.
D. Establish a push communications method for the team to share knowledge and lessons learned.

Answer explanation

B. Establish a pull communications method to access knowledge repositories and lessons learned

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.What should the project manager do next?
A. Discuss the list with the project sponsor to confirm that the resources have the required skills.
B. Ask the functional manager to review the resource pool and recommend the right individuals to join the team.
C. Meet with the project team to understand their skills and identify potential gaps and training requirements.
D. Send the list to the project team and ask them to get training on the required skills.

Answer explanation

C. Meet with the project team to understand their skills and identify potential gaps and training requirements

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client.What should the project manager do before sending the information to the client?
A. Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
B. Sequence the tasks with estimates and add standard risk reserves to use for software development.
C. Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
D. Work with the team to understand their views and add the appropriate dependencies and risks.

Answer explanation

This is D. You can't provide a prototype, at least a good one without consulting with the team first or even having any work done. The selected answer seems like the PM is doing everything without even talking with the team, and that's a recipe for failure.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
A. The product owner should not ask the team to change their sprint commitments.
B. The team is accepting too much work in the sprint after it has started.
C. The team is not meeting the expectations of the product owner.
D. The team should have stopped on day 4 and started a new sprint.

Answer explanation

B Looking at the chart, the team started with 10 tasks. On day 7, they completed those tasks, but 3 additional were added after the start. Had they not accepted those additional tasks, they would have been golden.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.What should the project manager do?
A. Continue the iteration and add the requested changes.
B. Continue the iteration and review the change with the customer.
C. Cancel the iteration and meet with the product owner.
D. Cancel the iteration and add the requested changes.

Answer explanation

B. Continue the iteration and review the change with the customer

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members.How should the project manager organize the WBS?
A. Customer oriented
B. Team oriented
C. Cost oriented
D. Deliverable oriented

Answer explanation

D is correct

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?