16 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refurbishment of a leisure centre with a swimming pool is taking place. An additional lighting circuit is to be installed. The new lights will be at a height of 2.4m above the pool.

What document must the Inspector use to record the new lighting circuit reference method?

Schedule of Test Results.

Schedule of Inspections.

Electrical Installation Schedule.

Electrical Installation Certificate.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refurbishment of a leisure centre with a swimming pool is taking place. An additional lighting circuit is to be installed. The new lights will be at a height of 2.4m above the pool. What would be the most appropriate human sense to use when inspecting the IP rating of the new lights?

Sight.

Smell.

Touch.

Hearing.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refurbishment of a leisure centre with a swimming pool is taking place. An additional lighting circuit is to be installed. The new lights will be at a height of 2.4 m above the pool.

What is the minimum IP rating required for the new lights?

IPX8

IPX5

IPX4

IPX2

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refurbishment of a leisure centre with a swimming pool is taking place. An additional lighting circuit is to be installed. The new lights will be at a height of 2.4 m above the pool.

What would be the most appropriate action to take if the new lights do not comply with the minimum IP rating?

Notify the client without delay.

Rectify the issue and re-inspect.

Record on the Schedule of Inspections.

Record on the Electrical Installation Certificate.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An existing installation in a hotel is to be inspected and tested as a requirement of the local authority for a public entertainment licence application. Previous inspection and testing records exist but two additional socket-outlet circuits have previously been installed for which there are no test results available.

What action should be taken with regard to the additional socket-outlet circuits?

Both should be sampled to check compliance with BS 7671.

One should be sampled to check compliance with BS 7671.

Both should be fully tested to check compliance with BS 7671.

One should be fully inspected to check compliance with BS 7671.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The continuity of a main protective bonding conductor to a gas installation pipe in a new primary school is to be tested. The 10 mm² conductor is 43 m long.

The installation has been safely isolated for this test. What instrument is to be used to carry out this test?

Low resistance ohmmeter.

Insulation resistance tester.

Approved voltage indicator.

Prospective fault current tester.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The continuity of a main protective bonding conductor to a gas installation pipe in a new primary school is to be tested. The 10 mm² conductor is 43 m long. The installation has been safely isolated for this test.

Which additional piece of test equipment will be required for this test?

Proving unit.

Rotating disc.

Wander lead.

Earth electrode.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?