1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a key output of the Validate Scope process?1. 1he product of the project has been completed and delivered to the customer by the team. They are informed by the customer that several of the deliverables are not acceptable, as they do not meet the requirements specified early in the project. The project manager and team review the requirements
documentation, and are in agreement that the product deliverables meet the customer's requirements as they understand them. The project manager, who is new to the organization, seeks the advice ofthe project management office in determining what went wrong. After some discussion, the PMO realizes that the Validate Scope process was not _performed appropriately by the project manager. Which of the following is a key output ofthe Validate Scope process?
A more complete scope management plan
Customer acceptance of project deliverables
Requirements analysis
Confirmation of the project scope statement
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
On an agile project, who is responsible for prioritizing the product backlog and keeping those priorities updated?
The project manager
The product owner or customer
Any interested stakeholder
The team leader
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The work breakdown structure can best be thought of as an effective aid for communications.
Team
Project manager
Customer
Stakeholder
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages?
WBS dictionary
Activity list
Project scope statement
Scope management plan
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During which part of the project management process is the project scope statement created?
Initiating
Planning
Executing
Monitoring and controlling
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project is mostly complete. The project has a schedule variance of 300 and a cost variance of -900. All but one of the quality control inspections have been completed, and all have met the quality requirements. All items in the issue log have been resolved. Many of the resources have been released. The sponsor is about to call a meeting to obtain product validation when the customer notifies the project manager that they want to make a major change to the scope. The project manager should:
Meet with the project team to determine if this change can be made.
Ask the customer for a description of the change.
Explain that the change cannot be made at this point in the process.
Inform management.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Marketing has asked for a copy of the plan for your agile project, including the release dates and the key features to be included in each release. What will you send them?
The team's product roadmap
A photo of the team's Kanban board
The first page of the product backlog
The product owner's requirements hierarchy
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?