1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Apa tujuan menggunakan PR untuk menghitung Performance?

Lebih menghighlight losses

Sama saja, hanya berbeda cara menghitung

Lebih mudah dihitung

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Apa kepanjangan dari PR?

Process Reliability

Process Redundancy

Public Relations

Planning Reliability

3.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Calendar Time dikurangi Non Staff Time Non Used adalah…

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Non Staff Time Non Used dan Staff Time Non Used merupakan…

SU Loss

PR Loss

Quality Loss

Target Rate Loss

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Scheduled Time adalah…

Maximum time within period

Time the production line could be scheduled to run

Time the production line is scheduled to run

Time the line producing sellable products

Time the line producing non-sellable products

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Apa yang tidak termasuk NTSNU?

Public Holiday

Non-Sellable Trials

Project Work

Non-Production Order

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Apa pembagi %NSTNU dan %STNU?

Calendar Time

Staffed Time

Scheduled Time

Net Production Time

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?