During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.What should the project manager do next in this situation?

200-300 F.T N

Quiz
•
Professional Development
•
1st Grade
•
Hard
Afghanistan Center
FREE Resource
22 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Review the project scope and negotiate with the contractor
Refuse the offer as it is included in the initial project scope
Review the project costs and communicate this to the project sponsor
Submit a change request to approve the offer
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path.What should the project manager do to avoid future delays?
Submit a change request.
Add additional resources to the project
Update the scope of work.
Review the risk management plan
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?
Ask the project sponsor for assistance in getting the budget back on track
Meet with the project team to analyze the actual cost to determine deviations
Inform the stakeholders that the project will be finished over budget.
Issue a change request including the analysis to increase the budget
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind scheduleWhat can the project manager do to move the team to the norming phase?
Plan social activities to help foster stronger interpersonal relationships and identify shared goals.
Speak with the project sponsor about changing the team composition
Figure out who is behind the issues and apply progressive disciplinary techniques.
Show the team the schedule impact of their communication issues and encourage them to put their
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget What should the project manager do next?
Request a replacement resource
Perform a cost-benefit analysis
Implement risk responses
Perform Integrated Change Control
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meetingWhat should the project manager do?
Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome
Update the communications management plan and implement the change
Meet with the project sponsor to discuss how to address the situation.
Meet with the stakeholder prior to the meeting to obtain their opinion
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities.How should the stakeholder be engaged in the project?
Keep the stakeholder informed and consult with them based on their needs
Involve the stakeholder in governance and decision making
Consult with the stakeholder and increase their level of interest
The stakeholder needs to be made aware of the project progress
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
Domain#3 Stakeholder Engagement Mike Griffith

Quiz
•
1st Grade
24 questions
PMI SH - Evaluate and Address External Business Environment Chan

Quiz
•
1st - 3rd Grade
21 questions
review of concepts -Module 2 (PM, sustainability and CSR)

Quiz
•
1st - 5th Grade
19 questions
Quality Induction Quiz

Quiz
•
1st Grade
20 questions
Domain#2 Value Driven Delivery Mike Griffith

Quiz
•
1st Grade
20 questions
Domain#7 Continuous Improvement Mike Griffith

Quiz
•
1st Grade
22 questions
PMI SH - Engage Stakeholders and Build Shared Understanding

Quiz
•
1st Grade
18 questions
PMI SH - Evaluate and Deliver Project Benefits and Value

Quiz
•
1st Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade