1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Felicia is an event project manager. She is meeting with her conference stakeholders to ensure the scope of products delivered aligns with what was planned for in the scope baseline of the project. Which process is Felicia conducting?
Collect requirements
Control scope
Define scope
Verify scope
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Jo Anne is meeting her curriculum team to break down pieces of the project. At the meeting, she leads her team through the process of decomposing to encompass all of the work on the project. This allows Jo Anne's team to track, define, and manage each activity. Jo Anne's team is participating in:
Collect requirements
Creating the WBS
Defining the scope
Verifying the scope
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Peter, a project manager, meets with his client to get the client's signature at the completion of a phase of work. Which phase is the project in?
Planning
Executing
Monitoring and controlling
Closing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sarah is in charge of a charity event, and she is currently communicating with the catering company and requesting work performance information regarding their progress to compare to her scope baseline. Sarah is working on which process?
Collect requirements
Control scope
Define scope
Verify scope
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Mark meets with the conference project stakeholders to determine and document that the number of rooms and meals needed for the conference aligns with the conference project objectives. Which process is Mark conducting?
Collect requirements
Control scope
define scope
verify scope
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Kacie is working on a new car design for an automotive company. She is currently working on a way to analyze, document, and manage all the stakeholder requirements for the new design. Kacie is working on the:
Requirements management plan
Requirements documentation
Requirements traceability matrix
Work breakdown structure
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Jackie is developing a document that will outline the methods to create and manage requirements, as well as the method used to prioritize requirements. Jackie is working on the:
Requirements documentation
Requirements management plan
Requirements traceability matrix
Work breakdown structure
Create a free account and access millions of resources
Similar Resources on Wayground
17 questions
24-25 PM1 Charter Creation & Decision Making

Quiz
•
9th - 12th Grade
17 questions
Use Business Technology

Quiz
•
9th - 12th Grade
20 questions
Business Management Final Review 2

Quiz
•
9th - 12th Grade
16 questions
BM 2.2 Review

Quiz
•
9th - 12th Grade
16 questions
U1- The Bus Environ- A2

Quiz
•
9th Grade - Professio...
20 questions
Nature of Ethics

Quiz
•
9th Grade
20 questions
WebXam Review - Principals of Business - 2 - Economic Principles

Quiz
•
9th - 12th Grade
20 questions
Resume Basics

Quiz
•
9th - 11th Grade
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade