Fast Track - Practice Test 1

Quiz
•
Other
•
3rd Grade
•
Hard
Afghanistan Center
Used 2+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control
How should the project manager report the project status to key stakeholders?
Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results
Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.
Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.
Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away
Answer explanation
Explanation: the one that reflects the best practice of communicating project status to stakeholders, based on the earned value management (EVM) metrics and the project management plan. Reference: PMP Exam Set G – Q76 - This is a similar question with the same answer choices and a detailed explanation of why each option is correct or incorrect.
It also provides a reference to the PMBOK Guide, Sixth Edition, page 267.
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level
What should the project manager do next with this opportunity?
A. Share this opportunity with another project
B. Establish a contingency reserve to support the opportunity
C. Further monitor the opportunity
D. No more action is required
Answer explanation
Explanation: This answer is based on the PMBOK® Guide, which is one of the reference materials for the PMP exam1. According to the guide, an opportunity is a positive risk or uncertain event or condition that, if it occurs, has a positive effect on one or more project objectives1. Opportunities can be identified and managed throughout the project life cycle, using various tools and techniques, such as risk identification, risk analysis, risk response planning, and risk monitoring and control1. When an opportunity is outside of the project scope, the project manager should update the risk register to document the opportunity and its potential impact, and escalate the opportunity to a higher level, such as the project sponsor, the portfolio manager, or the organization’s management1. The higher level can then decide whether to pursue the opportunity or not, and allocate the necessary resources and authority to do so1. The project manager should share the opportunity with another project that may benefit from it, or suggest a new project to exploit the opportunity1. The other options are not correct because they do not follow the best practices of opportunity management. Establishing a contingency reserve is a risk response strategy for negative risks, not positive ones1. Further monitoring the opportunity is not sufficient to realize its benefits, and may result in missing the opportunity or losing it to competitors1. No more action is required is not a proactive or responsible approach to managing opportunities,
and may imply a lack of interest or commitment to the project objectives1. References:
✑ PMBOK® Guide
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?
A. Work to understand the key stakeholder's concerns and provide feedback in regular project status reports
B. Arrange an ad hoc meeting to address the key stakeholder's concerns with team members
C. Reinforce with the key stakeholder that the project is performing on schedule
D. Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting
Answer explanation
Answer: A
Explanation: According to the PMBOK Guide, the project manager should manage stakeholder
they occur. This includes understanding the stakeholder’s concerns, interests, and expectations, and providing timely and accurate information to keep them informed and satisfied. By working to understand the key stakeholder’s concerns and providing feedback in regular project status reports, the project manager can maintain a positive relationship with the stakeholder and avoid unnecessary interruptions and conflicts. References: PMBOK Guide, 6th edition, page 540-541, section 13.3.2.4 Manage Stakeholder Engagement: Data Analysis.
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A. Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.
B. Review the project backlog looking for high-priority items and come up with a minimum viable product
C. Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule
D. Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the
Answer explanation
Answer: B
Explanation: According to the Professional in Business Analysis (PMI-PBA)® Guide, a minimum viable product (MVP) is a version of a product that has enough features to satisfy early customers and provide feedback for future development. A MVP is a way of delivering value to customers quickly and iteratively, while minimizing waste and risk. In this scenario, the project manager is faced with a drastic reduction in the project timeline, from 18 months to six months. This means that the original scope and schedule are no longer feasible, and the project manager needs to find a way to deliver a product that meets the customer’s needs and expectations within the new constraints. Reviewing the project backlog and prioritizing the
high-value items that can be delivered in six months is a sensible approach achieve this goal. The project manager can then work with the stakeholders to define and agree on the MVP that will provide the most value to the customer and the business. This option also allows for flexibility and feedback, as the MVP can
applying crashing and fast tracking, and sharing the risk of failure are options that try to compress the schedule without reducing the scope. These options may increase the cost, quality, and resource risks, and may not be acceptable to the stakeholders or the customer. Seeking approval to triple the project budget and hiring more people is an option that tries to increase the resources without reducing the scope. This option may not be feasible or realistic, as it assumes that the sponsor is willing and able to provide the additional funds, and that the project can benefit from adding more people in a short time. This option may also introduce communication, coordination, and integration challenges, and may not guarantee the delivery of the product in six months. Going over the critical path with stakeholders and explaining why it is not possible to deliver all the scope in the expected timeline is an option that tries to justify the original plan without considering alternatives. This option may not be satisfactory to the stakeholders or the customer, as it does not offer any solution or value proposition. This option may also damage the relationship and trust between the project manager and the stakeholders, and may result in the cancellation or termination of the project. Conclusion: Given the options, Option B stands out as the most viable and effective action.
Reviewing the project backlog and coming up with a MVP that fits the expected timeline addresses the customer’s needs and expectations, delivers value quickly and iteratively, and minimizes waste and risk. Among the presented choices, Option B emerges as the optimal solution. PMP Exam Content Outline Mapping Domain Task Process Task 2: Execute the project Topics Covered Minimum Viable Product (MVP) Project Backlog Prioritization Value Delivery References: (Professional in Business Analysis Reference Materials source and documents)
✑ Professional in Business Analysis (PMI-PBA)® Guide, Chapter 5, Section 5.3.1.2
✑ A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Chapter 5, Section 5.2.2.2
✑ The Standard for Project Management – Seventh Edition, Chapter 3, Section 3.2.2.2
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings
How should the project manager handle this?
A. Communicate directly with the director and inform them of the communications management plan
B. Communicate directly with the client stating that any scope changes must go through the project manager
C. Review the stakeholder engagement plan and put in place any existing actions accordingly
D. Discuss the issues with the project team and let them know that the project manager will handle scope
Answer explanation
Answer: A
Explanation: The project manager should communicate directly with the director and inform them of the communications management plan, which defines how the project information will be exchanged among stakeholders, including the client. By doing so, the project manager can clarify the roles and responsibilities of the project team and the director, and ensure that the project scope is managed according to the agreed process.
This will also help to avoid confusion, conflicts, and unauthorized changes in the project. References: (Professional in Business Analysis Reference Materials source and documents)
✑ PMBOK Guide, 6th edition, section 10.1.3.1, page 366
✑ PMP Exam Prep, 10th edition, Rita Mulcahy, page 357
✑ PMP Practice Questions #49 - iZenBridge1
6.
MULTIPLE SELECT QUESTION
3 mins • 1 pt
The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members
What two actions should project manager take? (Choose two)
A. Ask the team members to work it out themselves
B. Discuss this situation with other project managers and ask for advice
C. Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.
D. Address the behavioral issue with each team member
E. Discuss the behavior directly with their managers and request them to correct the behavior.
Answer explanation
Explanation: This answer is based on the PMBOK® Guide, which is one of the reference materials for the
PMP exam1, and the PMI Guide to Business Analysis, which is one of the reference materials for the PMI-PBA exam2. According to the guides, the project manager is responsible for managing the project team, which includes developing, leading, and motivating the team members, as well as resolving any conflicts or issues that may arise among them12. The project manager should also establish and enforce the ground rules for the project team, which are the agreed-upon standards of behavior and expectations
for the team members, such as communication protocols, decision-making processes, meeting guidelines, and conflict resolution methods12. When the project manager observes that two team members have been arguing with each other openly at meetings and bypassing the project manager to influence the sponsor, this indicates a serious breach of the ground rules and a potential threat to the project performance and harmony. The project manager should take the following two actions to address this situation:
✑ Reiterate ground rules at the next meeting and ensure that all team members are clear about these
rules. This action will remind the team members of their roles and responsibilities, and the expected norms of conduct for the project team. It will also reinforce the authority and accountability of the project manager, and the importance of following the agreed-upon procedures for communication and decision-making. This action will help to prevent further escalation of the conflict and restore trust and respect among the team members12.
✑ Address the behavioral issue with each team member. This action will allow the project manager to
understand the root cause of the conflict, and the perspectives and interests of each team member. It will also enable the project manager to provide constructive feedback, coaching, or counseling to each team member, and to facilitate a collaborative resolution that satisfies both parties and aligns with the project objectives. This action will help to improve the performance and morale of the team members, and to foster a positive and productive team culture12.
The other options are not appropriate because they do not address the problem effectively or ethically. Asking the team members to work it out themselves is not a responsible or proactive approach, as it may lead to further deterioration of the relationship and the project outcomes. Discussing this situation with other project managers and asking for advice is not a confidential or respectful way to handle the issue, as it may expose the team members to gossip or criticism, and undermine their trust and credibility. Discussing the behavior directly with their managers and requesting them to correct the behavior is not a fair or empowering way to deal with the issue, as it may create a perception of blame or punishment, and damage
✑ PMBOK® Guide
✑ PMI Guide to Business Analysis
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful
What should the project manager do in this scenario?
A. Develop a business case with assumptions for the new model
B. Develop a communications management plan to inform the employees about the new business model
C. Adopt an iterative rollout approach that delivers the highest business value earlier
D. Develop a detailed sprint plan with clear deliverables
Answer explanation
Answer: C
Explanation: An iterative rollout approach is a way of delivering a product or service incrementally, rather than in one big launch. This allows the project team to test and validate the product with real customers, get feedback, and make adjustments as needed. This reduces the risk of delivering a product that does not meet the customer’s needs or expectations, or that has major defects or errors. By delivering the highest business value earlier, the project team can also demonstrate the benefits of the new model to the executives and stakeholders, and gain their support and confidence. An iterative rollout approach is consistent with agile project management principles, which are recommended for high-risk and
high-uncertainty projects. References:
✑ The PMI Guide to Business Analysis Includes The Standard for Business Analysis, Chapter 5: Solution Evaluation, Section 5.3.2: Validate Solution
✑ Business Analysis for Practitioners: A Practice Guide, Chapter 7: Solution Evaluation, Section 7.3.2: Validate Solution
✑ Business Analysis Techniques: 72 Essential Tools For Success, Chapter 5: Strategy Analysis, Section
5.14: Incremental Delivery Planning
✑ Seven Steps to Mastering Business Analysis, Chapter 9: Solution Assessment and Validation, Section
9.3: Assess Proposed Solution
Create a free account and access millions of resources
Similar Resources on Wayground
16 questions
College Football Teams

Quiz
•
KG - Professional Dev...
25 questions
PCPS Future Problem Solving

Quiz
•
3rd - 6th Grade
21 questions
APU PPT Good Corporate Governance

Quiz
•
1st - 3rd Grade
21 questions
World Cup 2018

Quiz
•
3rd Grade
22 questions
manchester city

Quiz
•
KG - Professional Dev...
20 questions
Atlanta Braves

Quiz
•
KG - University
20 questions
Mini SG PMP

Quiz
•
3rd Grade
20 questions
CISM 4

Quiz
•
1st - 3rd Grade
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
10 questions
Afterschool Activities & Sports

Quiz
•
6th - 8th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
15 questions
Cool Tool:Chromebook

Quiz
•
6th - 8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
20 questions
Bullying

Quiz
•
7th Grade
18 questions
7SS - 30a - Budgeting

Quiz
•
6th - 8th Grade
Discover more resources for Other
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
13 questions
Place Value

Quiz
•
3rd Grade
10 questions
Place Value

Quiz
•
3rd Grade
18 questions
Rocks and Minerals

Quiz
•
3rd Grade
17 questions
Multiplication facts

Quiz
•
3rd Grade
20 questions
Parts of Speech

Quiz
•
3rd Grade
11 questions
Open Court Getting Started: Robinson Crusoe

Quiz
•
3rd Grade
20 questions
Capitalization Rules & Review

Quiz
•
3rd - 5th Grade