1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

Reinforce with the key stakeholder that the project is performing on schedule

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level.What should the project manager do next with this opportunity?

Share this opportunity with another project

Establish a contingency reserve to support the opportunity

Further monitor the opportunity

No more action is required

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.How should the project manager handle this?

Communicate directly with the director and inform them of the communications management plan

Communicate directly with the client stating that any scope changes must go through the project manager

Review the stakeholder engagement plan and put in place any existing actions accordingly

Discuss the issues with the project team and let them know that the project manager will handle scope changes

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members.What two actions should project manager take? (Choose two)

Ask the team members to work it out themselves

Discuss this situation with other project managers and ask for advice

Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.

Address the behavioral issue with each team member

Discuss the behavior directly with their managers and request them to correct the behavior.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful.What should the project manager do in this scenario?

Develop a business case with assumptions for the new model

Develop a communications management plan to inform the employees about the new business model

Adopt an iterative rollout approach that delivers the highest business value earlier

Develop a detailed sprint plan with clear deliverables

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.How can the project manager promote empowerment and accountability among the team?

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

Encourage and assign the team to perform demos of their products or software with the customers

Give the team autonomy to make their own decisions on how to perform the tasks.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?