
012 practice questions (A)
Authored by Ross Howell
Construction
Vocational training
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
36 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In order to undertake the inspection and testing of an electrical installation a person must, in law be a
Competent person
Principle person
Duty person
Registered person
Answer explanation
In law, a person undertaking the inspection and testing of an electrical installation must be a 'Competent person'. This designation ensures that the individual has the necessary skills and knowledge to perform the tasks safely and effectively.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The term ‘Dutyholder’ used in the Electricity at Work Regulations refer to a person:
Making the final payment on completion of the work
Responsible for the electrical installation
Reviewing the documents
Ordering the work
Answer explanation
The term 'Dutyholder' in the Electricity at Work Regulations specifically refers to the person responsible for the electrical installation, ensuring safety and compliance with regulations.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following identifies the correct process for safe isolation of a circuit protected by a circuit breaker?
Switch off, post notices
Switch off, lock off, post notices
Switch off, confirm isolation, post notices
Switch off, lock off, confirm isolation, post notices
Answer explanation
The correct process for safe isolation includes switching off the circuit, locking it to prevent re-energization, confirming isolation to ensure safety, and posting notices to inform others. Thus, 'Switch off, lock off, confirm isolation, post notices' is correct.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Work is to be carried out on an installation which includes a solar PV supply system. Which of the following must be carried out before isolating the DNO’s supply to the installation?
Isolate the Solar PV supply
Disconnect the installation loads
Close all switches
Disconnect the bonding conductors
Answer explanation
Before isolating the DNO's supply, it's crucial to isolate the Solar PV supply to prevent back-feeding electricity, ensuring safety during maintenance. This step protects both personnel and equipment.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A test of fault loop impedance is to be carried out in an area which is accessible to the public. Which of the following is not a suitable method of protecting the public from risk of electric shock?
Barriers
Warning signs
Safe isolation
Restricting access
Answer explanation
Safe isolation is not suitable for protecting the public from electric shock, as it involves working on live circuits. In contrast, barriers, warning signs, and restricting access effectively prevent public exposure to electrical hazards.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Work is to be carried out at the distribution board supplying a multi story office building. Which of the following must be placed out of service, to ensure the safety of users, before the safe isolation of the distribution board is carried out?
General lighting circuits
Air conditioning system
Lifts to all floors
Burglar alarms
Answer explanation
Lifts to all floors must be placed out of service to ensure user safety during work at the distribution board. This prevents any risk of users being trapped or injured while the power is isolated.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is most at risk when an inspector fails to isolate a lighting circuit before removing a luminaire cover to carry out inspection?
The inspector
Other operatives
The general public
The client
Answer explanation
The inspector is most at risk when failing to isolate a lighting circuit, as they could be exposed to live electrical components while removing the luminaire cover, leading to potential injury or electrocution.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
40 questions
Second Quarter Assessment Construction
Quiz
•
9th - 12th Grade
40 questions
MOT.05 -5
Quiz
•
KG - University
38 questions
Principles of Electricity
Quiz
•
12th Grade
33 questions
Understanding Superheat and Subcooling
Quiz
•
12th Grade
38 questions
General Carpentry: M4 Principles of Site and Building Layout
Quiz
•
11th Grade
32 questions
UTS Kewirausahaan
Quiz
•
University
40 questions
Rainwater Harvesting and Greywater Reuse
Quiz
•
11th Grade
35 questions
Carpentry and joinery
Quiz
•
Professional Development
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade