
Project Management Quiz 3
Authored by Hooi Lim
Education
University
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Approval for the project to proceed should be undertaken by:
The project sponsor
The project manager
The project team
The financier
Answer explanation
Approval of the project by the sponsor provides formal recognition. This is important for all size and types of projects – in particular for smaller projects whereby there may be a tendency toward simply allocating projects for implementation without any form of approval or acknowledgement by the sponsor.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A common technique used to depict the project’s scope is:
Critical path analysis
Gantt Chart
Work breakdown structure
Earned value management
Answer explanation
The most common technique is a Work Breakdown Structure (WBS) – usually hierarchical in nature. A WBS gives a visual representation of the major and sub-tasks that need to be completed.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project management integration requires the following order of task completion:
Scoping, cost estimation and scheduling
Scoping, scheduling and cost estimating
Cost estimating, scoping and scheduling
Scheduling, scoping and cost estimating
Answer explanation
Not only should the PM elements in the planning phase be integrated (i.e relate to each other) there should be a logical order for their completion. Ideally scoping and scheduling are completed before developing the budget.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project management plan is:
A diagram that depicts the sequencing of project activities
A document that depicts a breakdown of the activities to be undertaken
A document that specifies the project requirements
A document to help guide the project during implementation
Answer explanation
The Project Management Plan (PMP) should be seen as a useful management tool for the PM to manage the project over the life. It is developed during the planning stage so that the project manager has an overview of all of the deliverables.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The critical path of a project is normally identified using:
Project requirements listing
Work breakdown structure
Cost estimate
Sequencing the activities
Answer explanation
Critical path analysis is a common project management technique that can be used to determine the optimal duration or period of time for implementation of the project. It requires consideration of the ideal sequencing of the various activities that have been identified in the WBS. Some activities may need to be undertaken before other activities can be performed.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Developing the project schedule requires:
Sequencing activities
Estimating resources
Estimating duration
All of the above
Answer explanation
The schedule requires sequencing, then estimation of resources and duration in order to then determine the project duration.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project budget is:
The funds available to be spent
The approved estimate for the project
Funds borrowed for the project
None of the above
Answer explanation
With thorough planning, a project manager should be able to estimate the amount of money that will be needed to complete a project.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
Instructional Decision in Assessment
Quiz
•
University
20 questions
EDU321 Curriculum Studies II
Quiz
•
University
18 questions
21st Century Education
Quiz
•
University
10 questions
Usability & Accessibility
Quiz
•
University
12 questions
Educational Paradigms
Quiz
•
University
12 questions
LESSON 4: MY ROOM
Quiz
•
University
20 questions
QUIZ MPU22012 DKM5B
Quiz
•
University
20 questions
Kurikulum dan Pembelajaran
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
6 questions
Appropriate Chromebook Usage
Lesson
•
7th Grade
10 questions
Greek Bases tele and phon
Quiz
•
6th - 8th Grade
Discover more resources for Education
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
20 questions
Endocrine System
Quiz
•
University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
30 questions
W25: PSYCH 250 - Exam 2 Practice
Quiz
•
University
5 questions
Inherited and Acquired Traits of Animals
Interactive video
•
4th Grade - University
20 questions
Implicit vs. Explicit
Quiz
•
6th Grade - University
7 questions
Comparing Fractions
Interactive video
•
1st Grade - University
38 questions
Unit 8 Review - Absolutism & Revolution
Quiz
•
10th Grade - University