Search Header Logo

Project Management Quiz 3

Authored by Hooi Lim

Education

University

Used 2+ times

Project Management Quiz 3
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Approval for the project to proceed should be undertaken by:

The project sponsor

The project manager

The project team

The financier

Answer explanation

Approval of the project by the sponsor provides formal recognition. This is important for all size and types of projects – in particular for smaller projects whereby there may be a tendency toward simply allocating projects for implementation without any form of approval or acknowledgement by the sponsor.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A common technique used to depict the project’s scope is:

Critical path analysis

Gantt Chart

Work breakdown structure

Earned value management

Answer explanation

The most common technique is a Work Breakdown Structure (WBS) – usually hierarchical in nature. A WBS gives a visual representation of the major and sub-tasks that need to be completed.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project management integration requires the following order of task completion:

Scoping, cost estimation and scheduling

Scoping, scheduling and cost estimating

Cost estimating, scoping and scheduling

Scheduling, scoping and cost estimating

Answer explanation

Not only should the PM elements in the planning phase be integrated (i.e relate to each other) there should be a logical order for their completion. Ideally scoping and scheduling are completed before developing the budget.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project management plan is:

A diagram that depicts the sequencing of project activities

A document that depicts a breakdown of the activities to be undertaken

A document that specifies the project requirements

A document to help guide the project during implementation

Answer explanation

The Project Management Plan (PMP) should be seen as a useful management tool for the PM to manage the project over the life. It is developed during the planning stage so that the project manager has an overview of all of the deliverables.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The critical path of a project is normally identified using:

Project requirements listing

Work breakdown structure

Cost estimate

Sequencing the activities

Answer explanation

Critical path analysis is a common project management technique that can be used to determine the optimal duration or period of time for implementation of the project. It requires consideration of the ideal sequencing of the various activities that have been identified in the WBS. Some activities may need to be undertaken before other activities can be performed.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Developing the project schedule requires:

Sequencing activities

Estimating resources

Estimating duration

All of the above

Answer explanation

The schedule requires sequencing, then estimation of resources and duration in order to then determine the project duration.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project budget is:

The funds available to be spent

The approved estimate for the project

Funds borrowed for the project

None of the above

Answer explanation

With thorough planning, a project manager should be able to estimate the amount of money that will be needed to complete a project.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?