CLEAN : Ethiopia tests Sub Saharan Africa's first light rail system
Interactive Video
•
Physics, Science, Business
•
9th - 10th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the estimated headway time between trains during peak hours?
90 minutes
60 minutes
45 minutes
30 minutes
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of the dedicated line connector to the National Grid?
To increase train speed
To reduce ticket prices
To enhance passenger comfort
To prevent power fluctuations
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What scheme is used to design the power consumption for the light rail system?
Direct Current Scheme
Loop in Loop out Scheme
Alternating Current Scheme
Single Line Scheme
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What happens if there is a power cut in one of the traction substations?
The entire system shuts down
Trains run on backup batteries
The other substations compensate for the power loss
Passengers are evacuated
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main benefit of the Loop in Loop out scheme?
Increased train speed
Reduced maintenance costs
Avoidance of power interruptions
Lower energy consumption
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?