
PMP QUIZ 1
Authored by Michael Dennis
Business
Professional Development
10 Questions
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a high-risk project involving new technology. A critical supplier’s potential bankruptcy was identified as a risk during planning. To mitigate this, you negotiated contracts with multiple backup suppliers. However, one of these backups just withdrew their offer due to market conditions.
What should you do next?
Update the risk register and reassess risk response strategies.
Execute the contingency plan and procure from another backup supplier.
Revise the procurement management plan to secure additional backup vendors.
Conduct a qualitative risk analysis to reassess impact and probability.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project is behind schedule, and management asks you to recover lost time. The activity on the critical path with the longest duration has the highest resource dependency.
What is the best course of action?
Add more resources to the activity to fast-track the schedule
Crash the activity by allocating more skilled resources.
Reduce the scope of the activity to shorten duration.
Delay non-critical activities to reallocate resources to critical tasks.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project has an Earned Value (EV) of $350,000, a Planned Value (PV) of $400,000, and an Actual Cost (AC) of $370,000.
What do these numbers suggest?
The project is over budget and behind schedule.
The project is under budget but behind schedule.
The project is over budget but ahead of schedule.
The project is on track with planned costs and schedule.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During contract negotiations with a key supplier, legal disputes arise regarding liability for project delays. The supplier insists on a cost-plus-incentive-fee (CPIF) contract to cover their risk, but your company prefers a fixed-price contract for cost control.
What should you do?
Accept the CPIF contract to reduce supplier risk and avoid further delays.
Offer a time-and-materials (T&M) contract as a middle ground.
Escalate the issue to the project sponsor for resolution.
Negotiate performance-based incentives to align supplier goals with project success.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your cross-functional team disagrees on whether to prioritize system stability or innovation. The disagreement is delaying a critical design decision.
What is the most effective resolution strategy?
Use the forcing approach and make a decision yourself.
Collaborate with the team to find a balanced solution.
Allow the team to vote and accept the majority decision.
Refer to the project charter and let stakeholders decide.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your team identifies defects in a product during testing. These defects weren’t caught during earlier quality assurance checks.
What is the best corrective action?
Revise the quality assurance process to improve defect detection.
Perform additional quality control testing to catch future defects.
Conduct root cause analysis and document lessons learned.
Accept the defects as minor deviations and proceed with deployment.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A government regulation change introduces new compliance requirements that exceed your project’s contingency reserves.
What should you do first?
Escalate the issue to the sponsor since it’s beyond project scope.
Absorb the cost using available reserves and proceed.
Submit a change request to adjust the project baseline.
Perform a Monte Carlo simulation to reassess overall project risk.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
0 questions
Test Sprint 2
Quiz
•
0 questions
PMP Certification Exam Prep Quiz
Quiz
•
0 questions
PMI RMP - Risk Identification
Quiz
•
0 questions
PMP Exam Trial
Quiz
•
0 questions
pmp exam part 18
Quiz
•
0 questions
PMP Risk Management
Quiz
•
0 questions
PROJECT RISK MANAGEMENT
Quiz
•
0 questions
PMP Exam 61-120
Quiz
•
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Business
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
25 questions
Christmas Movies
Quiz
•
Professional Development
20 questions
Christmas Trivia
Quiz
•
Professional Development
15 questions
Fun Holiday Trivia
Quiz
•
Professional Development
25 questions
Name That Tune - Christmas
Quiz
•
Professional Development
29 questions
Christmas Song Emoji Pictionary
Quiz
•
Professional Development
9 questions
Holiday Movie Trivia
Lesson
•
Professional Development
34 questions
Winter Trivia
Quiz
•
Professional Development