Week3_Q1_Time Terms in Construction Project

Week3_Q1_Time Terms in Construction Project

University

15 Qs

quiz-placeholder

Similar activities

Project Delivery

Project Delivery

University

18 Qs

BQS601 INTRODUCTION

BQS601 INTRODUCTION

University

12 Qs

Professional Practice Quiz#2

Professional Practice Quiz#2

University

10 Qs

SITE VISIT QUIZ

SITE VISIT QUIZ

University

10 Qs

Key Players in Construction

Key Players in Construction

University

10 Qs

Standard of Professional Practice

Standard of Professional Practice

University

10 Qs

QUIZ FBC 2: introduction to fbc

QUIZ FBC 2: introduction to fbc

University

12 Qs

Quiz on Quantity Surveying

Quiz on Quantity Surveying

University

10 Qs

Week3_Q1_Time Terms in Construction Project

Week3_Q1_Time Terms in Construction Project

Assessment

Quiz

Architecture

University

Medium

Created by

Ana Ramdani

Used 3+ times

FREE Resource

15 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

30 sec • 6 pts

George Brown's project is more or less (1) .....

2.

FILL IN THE BLANK QUESTION

30 sec • 6 pts

The procurement (2)..... was quite tense as -

3.

FILL IN THE BLANK QUESTION

30 sec • 6 pts

... was quite tense as the tenders all only arrived (3).....

4.

FILL IN THE BLANK QUESTION

30 sec • 6 pts

Then the evaluation (4).... and a few items had to be negotiated with the lowest bidder.

5.

FILL IN THE BLANK QUESTION

30 sec • 6 pts

The pre-start meeting had to be (5).... by a week.

6.

FILL IN THE BLANK QUESTION

30 sec • 7 pts

Luckily the contractor (6) ...... by bringing ....

7.

FILL IN THE BLANK QUESTION

30 sec • 7 pts

... by bringing the (7).... to take possession of the site forward

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?