
1200-1300 Updated
Authored by Afghanistan Center
Professional Development
4th Grade
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project. What should the project manager, who is responsible for this project, do to mitigate this risk?
Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.
Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.
Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.
Assure the executive leadership team that the current governance model will not be affected by the agile approach.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns. What should the project manager do?
Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.
Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.
Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.
Create a record in the issue register and escalate the issue to the project steering committee.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval. What should the project manager do?
Plan a training session for the new team members not familiar with the system.
Communicate the rules and criteria to the team members through email.
Work only with the team members familiar with the system
Document which rules and criteria the new team members are not familiar with
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done. What should have been done to avoid this problem?
Included lessons learned from past projects
Used bottom-up estimating
Utilized three-point estimates
Validated the schedule performance index (SPI) to evaluate deviation
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team. What should the project manager do next?
Incorporate the changes in the last sprint before the first release.
Call for an internal meeting to discuss the changes and their value.
Ask the product owner to prioritize the backlog with the project team.
Request the scrum team to prioritize the product backlog.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?
Communicate the risk to the steering committee and request a mitigation plan from senior management.
Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.
Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.
Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria. How should the project manager ensure the acceptance criteria are met?
Perform tests and routinely track results as per the quality management plan.
Make sure the stakeholders are aware of the acceptance criteria.
Negotiate to obtain approval if most of the tests have passed.
Modify the acceptance criteria before the official delivery.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
27 questions
Oznakowanie
Quiz
•
1st - 5th Grade
35 questions
jaja
Quiz
•
1st - 5th Grade
25 questions
Contabilidad de costos Industria
Quiz
•
1st - 12th Grade
34 questions
Soal Cerita 34 Bakat
Quiz
•
1st - 10th Grade
25 questions
The Financial Free Zone Law 2
Quiz
•
KG - Professional Dev...
28 questions
MF1018 y MF249
Quiz
•
KG - Professional Dev...
25 questions
Name the DC Superheroes
Quiz
•
KG - University
25 questions
Angiospermas Reprodutivo
Quiz
•
1st - 10th Grade
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
Discover more resources for Professional Development
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
12 questions
Presidents' Day
Quiz
•
KG - 5th Grade
10 questions
History and Traditions of Valentine's Day
Interactive video
•
3rd - 6th Grade
14 questions
Fractions to Decimals & Decimals to Fractions
Quiz
•
4th Grade
18 questions
Valentines Day Trivia
Quiz
•
3rd Grade - University
77 questions
Mixed Multiplication and Division Facts
Quiz
•
4th Grade
10 questions
Data Collection
Quiz
•
4th Grade