1200-1300 Updated

1200-1300 Updated

4th Grade

30 Qs

quiz-placeholder

Similar activities

I GOT THE KEYS KEYS KEYS KEYS

I GOT THE KEYS KEYS KEYS KEYS

1st - 12th Grade

25 Qs

POST TES

POST TES

1st Grade - University

26 Qs

ILM Diploma level 5

ILM Diploma level 5

1st - 5th Grade

25 Qs

1000-1100 Updated

1000-1100 Updated

4th Grade

27 Qs

201-250/1706 Updated

201-250/1706 Updated

4th Grade

31 Qs

Project Management Quiz

Project Management Quiz

1st - 5th Grade

33 Qs

Lesson 4: Creating a Social Media Campaign

Lesson 4: Creating a Social Media Campaign

KG - Professional Development

28 Qs

Barcelona fc

Barcelona fc

1st Grade - University

28 Qs

1200-1300 Updated

1200-1300 Updated

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project. What should the project manager, who is responsible for this project, do to mitigate this risk?

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns. What should the project manager do?

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

Create a record in the issue register and escalate the issue to the project steering committee.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval. What should the project manager do?

Plan a training session for the new team members not familiar with the system.

Communicate the rules and criteria to the team members through email.

Work only with the team members familiar with the system

Document which rules and criteria the new team members are not familiar with

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done. What should have been done to avoid this problem?

Included lessons learned from past projects

Used bottom-up estimating

Utilized three-point estimates

Validated the schedule performance index (SPI) to evaluate deviation

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team. What should the project manager do next?

Incorporate the changes in the last sprint before the first release.

Call for an internal meeting to discuss the changes and their value.

Ask the product owner to prioritize the backlog with the project team.

Request the scrum team to prioritize the product backlog.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?

Communicate the risk to the steering committee and request a mitigation plan from senior management.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria. How should the project manager ensure the acceptance criteria are met?

Perform tests and routinely track results as per the quality management plan.

Make sure the stakeholders are aware of the acceptance criteria.

Negotiate to obtain approval if most of the tests have passed.

Modify the acceptance criteria before the official delivery.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?