1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A construction project outlines all stages of building a new bridge in a detailed plan, with each phase executed sequentially without room for major changes.

predictive

adaptive

hybrid

respect

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

a clearly defined project and deadline, but with lots of variations

predictive

adaptive

hybrid

respect

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Defines exactly what work needs to be done

project charter

project scope

product backlog

statement of work

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Formal authorization for the project, states the end goal of the project (objectives), has the purpose, objectives, and milestones

project charter

project scope

product backlog

gold plating

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Difference between the original schedule and the current schedule

cost variance

gold plating

schedule variance

scope screep

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Shortest route to finish the project from start to finish, changes to the start and end date can effect this path and the time it takes to finish the project

procurement task

critical path

scope creep

WBS

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An external contractor hired to complete a task or provide a service

vendor

sponsor

manager

boss lady

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?