Project Management Week 7 Quiz

Project Management Week 7 Quiz

12th Grade

15 Qs

quiz-placeholder

Similar activities

Financial Aid Basics

Financial Aid Basics

9th Grade - University

20 Qs

ENGLISH BUSINESS VERBS

ENGLISH BUSINESS VERBS

10th Grade - Professional Development

10 Qs

17 Days of SDGs Quiz - Day 10 (English)

17 Days of SDGs Quiz - Day 10 (English)

KG - Professional Development

15 Qs

Making Learning Active and Engaging

Making Learning Active and Engaging

KG - University

10 Qs

Chain of Command - NJROTC

Chain of Command - NJROTC

9th Grade - Professional Development

18 Qs

Analysis of financial statement 1

Analysis of financial statement 1

12th Grade

10 Qs

Microsoft Excel

Microsoft Excel

KG - Professional Development

20 Qs

17 Days of SDGs Quiz - Day 11 (English)

17 Days of SDGs Quiz - Day 11 (English)

3rd Grade - Professional Development

15 Qs

Project Management Week 7 Quiz

Project Management Week 7 Quiz

Assessment

Quiz

Professional Development

12th Grade

Practice Problem

Medium

Created by

ayomide owokade

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a key activity during the Execution Phase of a project?

Defining project scope

Resource Coordination

Risk Identification

Stakeholder Identification

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which phase of the project management lifecycle is project performance continuously monitored?

Initiation Phase

Planning Phase

Monitoring and Control Phase

Closing Phase

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What schedule compression technique involves adding more resources to critical path activities?

Fast Tracking

Crashing

Scope Creep

Risk Mitigation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Earned Value Management (EVM), what does PV stand for?

Project Value

Planned Variance

Planned Value

Performance Value

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the last phase of the project management lifecycle?

Execution Phase

Monitoring and Control Phase

Planning Phase

Closing Phase

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Software Development Lifecycle (SDLC) includes which of the following phases?

Ideation, Design, Development, Testing, Deployment, Maintenance

Planning, Execution, Monitoring, Closing

Initiation, Planning, Execution, Control

Definition, Design, Development, Delivery

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a core value of the Agile Manifesto?

Comprehensive documentation over working software

Process and tools over individuals and interactions

Customer collaboration over contract negotiation

Following a plan over responding to change

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development