Project Management Week 7 Quiz

Project Management Week 7 Quiz

12th Grade

15 Qs

quiz-placeholder

Similar activities

Time and project management

Time and project management

12th Grade

14 Qs

career_advancement

career_advancement

KG - Professional Development

10 Qs

SO Fast SO  Curious

SO Fast SO Curious

1st Grade - University

15 Qs

Charter 101 Follow up

Charter 101 Follow up

9th - 12th Grade

16 Qs

Quiz Pelatihan Scrum ASN

Quiz Pelatihan Scrum ASN

1st - 12th Grade

10 Qs

EPIC Proj Mgmt Plan

EPIC Proj Mgmt Plan

9th - 12th Grade

18 Qs

Agile PM#1 Quiz

Agile PM#1 Quiz

1st Grade - University

20 Qs

Project management and Execution

Project management and Execution

1st Grade - Professional Development

10 Qs

Project Management Week 7 Quiz

Project Management Week 7 Quiz

Assessment

Quiz

Professional Development

12th Grade

Medium

Created by

ayomide owokade

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a key activity during the Execution Phase of a project?

Defining project scope

Resource Coordination

Risk Identification

Stakeholder Identification

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which phase of the project management lifecycle is project performance continuously monitored?

Initiation Phase

Planning Phase

Monitoring and Control Phase

Closing Phase

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What schedule compression technique involves adding more resources to critical path activities?

Fast Tracking

Crashing

Scope Creep

Risk Mitigation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Earned Value Management (EVM), what does PV stand for?

Project Value

Planned Variance

Planned Value

Performance Value

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the last phase of the project management lifecycle?

Execution Phase

Monitoring and Control Phase

Planning Phase

Closing Phase

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Software Development Lifecycle (SDLC) includes which of the following phases?

Ideation, Design, Development, Testing, Deployment, Maintenance

Planning, Execution, Monitoring, Closing

Initiation, Planning, Execution, Control

Definition, Design, Development, Delivery

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a core value of the Agile Manifesto?

Comprehensive documentation over working software

Process and tools over individuals and interactions

Customer collaboration over contract negotiation

Following a plan over responding to change

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?