1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
1. When testing a drainage system, the system should be filled with water or air for a minimum of:
a. 15 minutes.
b. 30 minutes.
c. 1 hour.
d. 2 hours.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
2. When using water to test a drainage system the maximum feet of head allowed is:
a. 10 feet.
b. 20 feet.
c. 30 feet.
d. 40 feet.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
3. When testing gas piping, you use:
a. Water
b. Natural Gas
c. Carbon dioxide, nitrogen, air
d. Oxygen
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
4. Test gauges shall not have a pressure range more than ______ the test pressure.
a. equal
b. twice
c. 15 psi
d. 60 psi
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
5. Except for plastic piping, water piping systems may be tested with ________________________.
a. 10 psi air pressure
b. 50 psi air pressure
c. 10 psi CO2
d. 60 psi CO2
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
6. Except for plastic pipe, in lieu of water test, drainage piping may be tested with _________________.
a. air
b. ether
c. smoke
d. gas
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
7. Schedule 40 plastic DWV systems shall not be tested by _____________.
a. water
b. air
c. 10-foot head of water
d. water from low to high point
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?