Basic Concepts and Formatting & Printing

Basic Concepts and Formatting & Printing

University

10 Qs

quiz-placeholder

Similar activities

Division 10+ Review

Division 10+ Review

University

13 Qs

Bidding

Bidding

University

10 Qs

Greywater & McHP

Greywater & McHP

2nd Grade - University

15 Qs

 Drainage - Pipe materials and falls

Drainage - Pipe materials and falls

11th Grade - University

10 Qs

Młodociany co wolno co nie wolno :)

Młodociany co wolno co nie wolno :)

1st Grade - University

10 Qs

Health and Safety Executive (HSE) Quiz

Health and Safety Executive (HSE) Quiz

12th Grade - University

15 Qs

Plumbing Systems Decommissioning Quiz

Plumbing Systems Decommissioning Quiz

12th Grade - University

13 Qs

Untitled Quiz

Untitled Quiz

9th Grade - University

5 Qs

Basic Concepts and Formatting & Printing

Basic Concepts and Formatting & Printing

Assessment

Quiz

Construction

University

Easy

Created by

Gabriel Gurrola

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of project management software?

Writing documents

Managing schedules and tasks

Sending emails

Creating spreadsheets

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be the first step when setting up a new project?

Entering all tasks manually

Setting the project start date

Assigning resources

Printing the schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which relationship type ensures that a task starts only after the previous task is completed?

Finish-to-Start (FS)

Start-to-Start (SS)

Finish-to-Finish (FF)

Start-to-Finish (SF)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of using lag in task scheduling?

To delay the start of a task

To shorten project duration

To assign more resources

To remove dependencies

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done to ensure the Gantt chart fits on one page when printing?

Use default settings

Adjust page scaling in print settings

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which columns are typically included when printing a project schedule?

A) Task Name, Start Date, Finish Date

B) Task Mode, Task Name, Duration, Start, Finish, Predecessors

C) Task Mode, Cost, Duration, Notes

D) Predecessors, Resources, Start Date

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a milestone in project scheduling?

A) A task with a specific duration

B) A point marking a significant event in the project

C) A task requiring multiple resources

D) A recurring task

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?