Basic Concepts and Formatting & Printing

Basic Concepts and Formatting & Printing

University

10 Qs

quiz-placeholder

Similar activities

Introduction to ADR

Introduction to ADR

University

15 Qs

Project Planning

Project Planning

University

10 Qs

USCS with Zahid

USCS with Zahid

University

15 Qs

Medellín

Medellín

1st Grade - University

10 Qs

Risk, Documents, Specifications, EIA

Risk, Documents, Specifications, EIA

University

10 Qs

Construction Management Principles

Construction Management Principles

University

7 Qs

Basic Concepts and Formatting & Printing

Basic Concepts and Formatting & Printing

Assessment

Quiz

Construction

University

Easy

Created by

Gabriel Gurrola

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of project management software?

Writing documents

Managing schedules and tasks

Sending emails

Creating spreadsheets

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be the first step when setting up a new project?

Entering all tasks manually

Setting the project start date

Assigning resources

Printing the schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which relationship type ensures that a task starts only after the previous task is completed?

Finish-to-Start (FS)

Start-to-Start (SS)

Finish-to-Finish (FF)

Start-to-Finish (SF)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of using lag in task scheduling?

To delay the start of a task

To shorten project duration

To assign more resources

To remove dependencies

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done to ensure the Gantt chart fits on one page when printing?

Use default settings

Adjust page scaling in print settings

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which columns are typically included when printing a project schedule?

A) Task Name, Start Date, Finish Date

B) Task Mode, Task Name, Duration, Start, Finish, Predecessors

C) Task Mode, Cost, Duration, Notes

D) Predecessors, Resources, Start Date

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a milestone in project scheduling?

A) A task with a specific duration

B) A point marking a significant event in the project

C) A task requiring multiple resources

D) A recurring task

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?