
651-700 Updated
Authored by Afghanistan Center
Professional Development
1st Grade

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
32 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the planning for a long project, the project manager recognized that several members of the team are new to their roles. How should the project manager incorporate this into planning?
Increase the overall project duration to account for the inexperienced team members on the project.
Ensure planning has accounted for replacing team members in new project roles who do not deliver on project goals.
Assess the training requirements and ensure time for professional development training by senior members.
Revisit the project resource allocation to remove the inexperienced team members assigned to the project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team has started a new project. When should the project manager organize their first team retrospective?
When the team completes a release of a monumental increment
When the team reaches a major milestone
When more than a few weeks have passed
When the work is progressing well through the team
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line. What should the project manager do first?
Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.
Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.
Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.
Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A developer who has almost completed a required product feature for a prototype leaves the company in the middle of an iteration. What should the project manager do?
Review the backlog to reschedule the deliverable for a later iteration.
Engage with stakeholders directly to review the iteration process.
Determine whether other cross-functional team members are able to take over the work.
Go to management and ask to hire a new external developer.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release. What tools should the agile project manager use to do these estimates?
Product backlog, budget, resource management plan
Budget, minimum viable product (MVP), retrospective notes
Resource management plan, retrospective notes, backlog grooming
Backlog grooming, product backlog, minimum viable product (MVP)
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project. How should the project manager adjust their responsibilities accordingly?
Become a servant leader by supporting team collaboration and removing impediments
Delegate coordination activities to the product owner so the project manager can locus on managing collaboration
Request a scrum master to focus on the collaboration while the project manager focuses on the coordination
Introduce new communication tools to the project team members
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule. What should the project manager do first?
Perform an impact analysis with subject matter experts (SMEs).
Inform the government representative about the impact of the separate project.
Implement a change request to increase the budget and schedule.
Consult and update the risk register with the project stakeholders.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
30 questions
TKMRPI (0526)
Quiz
•
KG - Professional Dev...
30 questions
Zapasy w magazynie
Quiz
•
1st Grade
34 questions
Anatomía de maxilar y mandíbula
Quiz
•
1st Grade
27 questions
Back to School Fun!
Quiz
•
KG - 11th Grade
30 questions
Additive Manufacturing Assessment-1
Quiz
•
1st - 3rd Grade
30 questions
SANDI MORSE
Quiz
•
1st Grade - University
37 questions
El cosmético
Quiz
•
1st - 3rd Grade
28 questions
Lernfeld 1 Quiz
Quiz
•
1st Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Professional Development
20 questions
Telling Time to the Hour and Half hour
Quiz
•
1st Grade
10 questions
Life Cycle of a Frog
Quiz
•
1st - 2nd Grade
10 questions
Exploring Rosa Parks and Black History Month
Interactive video
•
1st - 5th Grade
20 questions
Place Value
Quiz
•
KG - 3rd Grade
10 questions
100th Day of School 1st/2nd
Quiz
•
1st - 2nd Grade
15 questions
Reading Comprehension
Quiz
•
1st - 5th Grade
10 questions
Identifying Physical and Chemical Changes
Interactive video
•
1st - 5th Grade
10 questions
Exploring the American Revolution
Interactive video
•
1st - 5th Grade