651-700 Updated

651-700 Updated

1st Grade

32 Qs

quiz-placeholder

Similar activities

Program Benefits Management

Program Benefits Management

1st Grade

30 Qs

Managment

Managment

1st - 12th Grade

30 Qs

601-650 Updated

601-650 Updated

1st Grade

28 Qs

PMI SH - Support Team Performance by Providing Adequate Training

PMI SH - Support Team Performance by Providing Adequate Training

1st - 3rd Grade

27 Qs

PMI SH - Mentor and Collaborate With Stakeholders

PMI SH - Mentor and Collaborate With Stakeholders

1st - 3rd Grade

31 Qs

Pre-Test Day1

Pre-Test Day1

1st - 3rd Grade

30 Qs

Project Management Part 3

Project Management Part 3

1st Grade

32 Qs

Program Stakeholder Engagement

Program Stakeholder Engagement

1st Grade

36 Qs

651-700 Updated

651-700 Updated

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

Afghanistan Center

FREE Resource

32 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the planning for a long project, the project manager recognized that several members of the team are new to their roles. How should the project manager incorporate this into planning?

Increase the overall project duration to account for the inexperienced team members on the project.

Ensure planning has accounted for replacing team members in new project roles who do not deliver on project goals.

Assess the training requirements and ensure time for professional development training by senior members.

Revisit the project resource allocation to remove the inexperienced team members assigned to the project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team has started a new project. When should the project manager organize their first team retrospective?

When the team completes a release of a monumental increment

When the team reaches a major milestone

When more than a few weeks have passed

When the work is progressing well through the team

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line. What should the project manager do first?

Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.

Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.

Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.

Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A developer who has almost completed a required product feature for a prototype leaves the company in the middle of an iteration. What should the project manager do?

Review the backlog to reschedule the deliverable for a later iteration.

Engage with stakeholders directly to review the iteration process.

Determine whether other cross-functional team members are able to take over the work.

Go to management and ask to hire a new external developer.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release. What tools should the agile project manager use to do these estimates?

Product backlog, budget, resource management plan

Budget, minimum viable product (MVP), retrospective notes

Resource management plan, retrospective notes, backlog grooming

Backlog grooming, product backlog, minimum viable product (MVP)

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project. How should the project manager adjust their responsibilities accordingly?

Become a servant leader by supporting team collaboration and removing impediments

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

Introduce new communication tools to the project team members

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule. What should the project manager do first?

Perform an impact analysis with subject matter experts (SMEs).

Inform the government representative about the impact of the separate project.

Implement a change request to increase the budget and schedule.

Consult and update the risk register with the project stakeholders.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?