CAPM Practice Tests - Business Analysis Frameworks

Quiz
•
Professional Development
•
Professional Development
•
Easy

Patrick Pepin
Used 2+ times
FREE Resource
Student preview

25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project sponsor expressed concerns to the project manager about whether the resulting product would meet business needs. Therefore, the project sponsor is looking to keep costs to a minimum.
What should the project manager do?
Identify and implement the requirements for making a Minimum Viable Product (MVP).
Gather all requirements and execute the project using an incremental approach.
Exclude certain stakeholders from the scope definition process in order to limit requirements.
Sign with the sponsor a fixed-cost contract to limit project costs.
Answer explanation
The Minimum Viable Product (MVP) is used to define the scope of the first release by identifying the requirements that would deliver value to customers (PMBOK Guide 7th Edition, page 243).
Option B: An incremental approach is not suitable for the described scenario since the client won't get a usable product until the end of the project. It's not appropriate to exclude certain stakeholders in order to limit requirements.
Option C: The project manager should involve all stakeholders in the process of collecting and prioritizing product features.
Option D: A fixed-cost contract will not solve the problem in the described scenario since the main concern of the sponsor is verifying the product's business demand.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager determines viable options and provides recommendations about the investment efficiency of two potential projects by implementing valuation techniques. Knowing that the discount rate is unknown, what should the project manager do?
Choose the project that has the highest ROI
Choose the project that has the lowest ROI
Choose the project that has the highest NPV
Choose the project that has the lowest NPV
Answer explanation
Calculating a project's Net Present Value (NPV) requires knowing its discount rate (i):
Net Present Value (NPV) = Future payment (F) / | (1 + Discount rate (i) ) ^ number of periods in the future the cash flow is (n) ].
Since this is not an option in the described scenario, the project manager should rely on the Return On Investment (ROI) and pick the project with the highest value. (The PMI Guide to Business Analysis, page 90)
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization is considering two potential projects with identical payback periods. After conducting a benefit measurement analysis, the project manager discovers that Project B has a higher Internal Rate of Return (IRR) than Project A. Which project should the organization select?
Project A
Project B
There is no difference
The available information is not enough to make a decision
Answer explanation
The Internal Rate of Return is the annual rate of growth a project is expected to generate.
The higher the IRR, the more desirable an investment is. Project B has a higher IRR, thus it will obviously be selected over Project A.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The customer sends the project manager a document outlining the new project's requirements. While checking the document, the project manager struggles to understand some of the requirements, outputs, and especially the ultimate goal of the project. What should the project manager do next?
Ask the customer for clarification
Reject the new project as it involves a lot of ambiguity
Start planning the first iteration
Acquire a team to help analyze the project requirements
Answer explanation
In case of ambiguity, the project manager should first ask for clarifications from the customer before making any further decisions.
Option C: The project involves unclear requirements and objectives. Thus, it's not appropriate to start planning project work or acquire a team without first creating a clear vision of what the project consists of.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To guide the development team on what they intend to achieve, a product owner provides a table that includes the key deliverables of each quarter of the 9-month project. What artifact does this table represent?
Product vision statement
Product wireframe
Product roadmap
Product backlog
Answer explanation
A product roadmap is a strategic plan that highlights the key components of a product that are scheduled for delivery across a portfolio, program, or several project iterations or releases, including the likely order in which these components will be delivered (The PMI Guide to Business Analysis, page 55).
The product roadmap indicates where the product is headed in both the short and long terms. In agile organizations, the product roadmap serves as a guide rather than a project plan.
Option A: A product vision statement outlines what a product would look like to ultimately achieve its vision and give purpose to its existence. A vision statement should be short, simple, and specific.
Option B: The Product wireframe is a mockup or a sketch of the user interface, high-level functionality, page layout, etc.
Option D: The product roadmap is different from the product backlog in that the product roadmap provides the big picture while the product backlog tackles the practical and feasible steps required to tangibly create the product.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A business analyst is eager to implement a new solution for the company. The stakeholders requested an assessment of the business value it will bring.
What should the business analyst do?
Conduct a cost-benefit analysis
Use a benchmarking technique
Conduct a feasibility study
Conduct a feature injection
Answer explanation
A cost-benefit analysis evaluates the financial return of implementing the solution by comparing the expected benefits against the costs. It's an effective way to assess the business value of a solution.
Option B: Benchmarking typically involves comparing a company's performance or processes to industry standards or best practices. While useful for understanding relative performance, it doesn't directly assess the specific business value of a new solution.
Option C: A feasibility study assesses whether a project or solution is viable and can be successfully implemented. It focuses more on the practicality of the solution rather than its business value.
Option D: Feature injection involves breaking down and analyzing features to understand their value and implementation. While this can help in understanding specific aspects of a solution, it doesn't directly assess the overall business value.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project team finds out that several implemented features deviate from what is specified in the scope statement.
Which document should the project manager consult to address the issue?
WBS
WBS dictionary
Requirements traceability matrix
Project charter
Answer explanation
The traceability Matrix is a document that maps requirements as well as other aspects of the project.
It's used as evidence to confirm that requirements have been fulfilled, as it typically documents those requirements along with issues and test results (PMBOK Guide 7th Edition, page 189).
Create a free account and access millions of resources
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade