GANTT CHART & SITE LAYOUT

Authored by Bazz Jill

Construction

Vocational training

Used 3+ times

GANTT CHART & SITE LAYOUT
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a reason why planning in advance of the construction project has been rapidly developing?

Fluctuating oil prices

Increasing global warming

Increase in work competition

Larger and more complex projects

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the definition of the Method Statement?

The statement lists the financial breakdown of the activity.

The statement arranges ideas of how contracts are executed.

The statement clarifies the organisational chart of the project.

The document lists down the contractors and labourers of the activity.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In creating Bar/Gantt Charts, what do we mean by the term “Work Schedule”?

Time framework for the project plan.

Method to select a suitable contractor.

Document used to verify any payments.

System used to monitor workers’ attendance.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Bar/Gantt Chart, what does the use of different colours represent?

To ensure that the contractors remain competent.

 

 

To identify the tasks of contractors and subcontractors.

To allow comparison between scheduled and built progress.

To prevent any construction accidents from occurring on site.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the most widely accepted method of presenting technically the work schedule activities sequence and time duration information?

Layout Diagram

Bar or Gantt Chart

Sales invoice document

Tender information billing

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In terms of construction, why do we need to prepare the Method Statement?

To give a suitable level of production flow.

To gauge the bonus for the workers’ salary.

To list properly the work organisational chart.

To select the most appropriate sub-contractors.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following example is NOT part of PPE (Personal Protective Equipment)?

Gloves

Dust masks

Hearing aid

Respirators

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?