**FE __M2 _O2

**FE __M2 _O2

1st Grade

40 Qs

quiz-placeholder

Similar activities

Emotion, People 4, Fashion Vocabulary Quiz

Emotion, People 4, Fashion Vocabulary Quiz

KG - 8th Grade

42 Qs

VOCABULARY TỔNG HỢP 1-10

VOCABULARY TỔNG HỢP 1-10

1st Grade - University

43 Qs

Examen A1 beginners

Examen A1 beginners

1st Grade

40 Qs

A2+ Exam 1

A2+ Exam 1

1st - 11th Grade

35 Qs

U3L2 Review

U3L2 Review

KG - University

40 Qs

chapter 1B realidades

chapter 1B realidades

1st - 12th Grade

43 Qs

los números 0-100

los números 0-100

KG - University

45 Qs

Arts and Me

Arts and Me

KG - 12th Grade

43 Qs

**FE __M2 _O2

**FE __M2 _O2

Assessment

Quiz

World Languages

1st Grade

Practice Problem

Easy

Created by

Renato Santos

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Visual representations of the major start

or finish of events associated with the

project plan.

Gantt Chart

Project Schedules

Project Milestone

PERT-CPM

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The connecting of project activities

with relationships or logical ties.

Relationships

Dependencies

Connectivity

Reliance

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An accurate representation of

how long an activity should take.

Lead Time

Schedule

Milestones

Duration

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The time it takes for critical

materials or equipment to arrive

on a project site.

Delivery Schedule

Lead Time

Lag Time

Waiting Period

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The positive or negative duration tied to

a relationship or logical tie between two

work activities.

Lead Time

Schedules

Lag Time

Time Allowance

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A calculated value/amount of time that a

scheduled activity can be delayed

without delaying the start date of any

following activity.

Lag Time

Lead Time

Float

Due Time

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Determining the resources needed for a

project and the timeline for completing

each project task that considers the

availability of those resources.

Resource Plan

Resource Management

Resource Allocation

Resource Analysis

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?