Which statement best describes the purpose of a project diary/logbook?

Project Execution and Monitoring Concepts Quiz

Quiz
•
Engineering
•
University
•
Hard

Martin Dufficy
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
It provides a Gantt chart view of tasks.
It records daily or weekly progress and any issues faced.
It is used exclusively for financial management.
It acts as a code of ethics for project teams.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When updating a Gantt chart due to unexpected delays, you should primarily:
Erase all previous tasks and start from scratch.
Wait until the end of the project to incorporate changes.
Adjust task durations, dependencies, or milestones as soon as the delay is known.
Keep the chart unchanged to maintain the original baseline.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A cost variance indicates that:
The project team has new ethical standards to follow.
Actual spending differs from the planned or budgeted costs.
Some tasks have better safety equipment than others.
The Gantt chart needs to be reset to zero.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is an example of a Schedule Variance?
Finishing a task 2 days behind the planned date.
Exceeding the planned budget by 10%.
Having fewer defects than expected during testing.
Changing stakeholders mid-project.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why might you need to adapt your resource allocation mid-project?
Because resource allocation is never done at the start of a project.
To ensure ethical standards are in place.
In response to unexpected changes like staff shortages or new client requests.
To remove constraints on the project entirely.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A high defect rate in the manufacturing stage suggests:
The project is under budget.
The tasks are likely ahead of schedule.
Quality is suffering, requiring root-cause analysis and potential redesign.
The project team has no accountability.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which monitoring approach specifically compares actual progress to planned milestones in real time?
Ethical review board.
Gantt chart updates.
Discarding the timeline and focusing on cost only.
Brainstorming new features each week.
Create a free account and access millions of resources
Similar Resources on Quizizz
12 questions
Project Cost Management

Quiz
•
University
12 questions
Methods of Estimating Quiz

Quiz
•
University
15 questions
Value Engineering

Quiz
•
12th Grade - University
10 questions
BASIS MPC

Quiz
•
University
13 questions
FlexSim Quiz Assessment 2

Quiz
•
University
14 questions
Lesson 1 Introduction to PLC

Quiz
•
University
10 questions
Precision and Accuracy

Quiz
•
10th Grade - University
8 questions
DERN 1322 - Health & Hygiene

Quiz
•
University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade