Project Management with Microsoft projects

Project Management with Microsoft projects

University

6 Qs

quiz-placeholder

Similar activities

Project management

Project management

University

10 Qs

Laravel True or False Quiz 1

Laravel True or False Quiz 1

University

10 Qs

Quiz 6 - Managing Software Development

Quiz 6 - Managing Software Development

University

5 Qs

Understanding Database Normalisation Concepts

Understanding Database Normalisation Concepts

11th Grade - University

10 Qs

Scope Management

Scope Management

University - Professional Development

10 Qs

Computer world. Inside and Outside

Computer world. Inside and Outside

KG - Professional Development

10 Qs

Soal LCC 2-Sistem Operasi

Soal LCC 2-Sistem Operasi

10th Grade - University

10 Qs

Quiz Modul 5 Ms Project

Quiz Modul 5 Ms Project

University

10 Qs

Project Management with Microsoft projects

Project Management with Microsoft projects

Assessment

Quiz

Computers

University

Medium

Created by

Daneillia Burke

Used 2+ times

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 1: 2 truths one Lie. Find the incorrect phrase.

  1. Microsoft Project allows you to create task dependencies like Finish-to-Start and Start-to-Finish.

  2. Microsoft Project automatically generates Gantt charts without requiring any data input.

  3. You can assign resources such as people, equipment, and materials to tasks in Microsoft Project.

A

B

C

2.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 2: TWO TRUTHS ONE LIE. FIND THE INCORRECT PHRASE

  1. You can set milestones in Microsoft Project by assigning a task with a duration of zero days.

  2. Microsoft Project allows you to track actual task progress by percentage completion.

  3. Microsoft Project automatically adjusts project timelines based on delays without user intervention.

A

B

C

3.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 3: Two truths one lie. Find the incorrect phrase

  1. You can assign deadlines to tasks to ensure they are completed by a specific date in Microsoft Project.

  2. Microsoft Project only supports one view of the project at a time.

  3. Task dependencies in Microsoft Project can be set to different types such as Finish-to-Start and Start-to-Start.

A

B

C

4.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 4:

A) You can update a task's status by entering the percentage of completion in the "Percentage Complete" field in Microsoft Project.

B) The Gantt Chart view in Microsoft Project shows tasks, dependencies, and overall project progress visually.

c) In Microsoft Project, once a project is started, you cannot modify the task durations or start dates.

A

B

C

5.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

Question 5: two truths one lie. Find the incorrect statement

A)Microsoft Project allows you to create task dependencies to determine the order in which tasks must be completed.

B)You can track resource utilization, such as how much work a resource has completed, in Microsoft Project.

C)Microsoft Project only allows tracking of tasks, not resources.

A

B

C

6.

MULTIPLE CHOICE QUESTION

45 sec • 20 pts

QUESTION 6: two truths one lie find the incorrect statement

A) Microsoft Project allows you to print reports such as progress reports and resource allocation reports.

B) You can set up project deadlines directly in the Gantt chart view.

C) Task information, including dates and resources, cannot be modified once entered in Microsoft Project.

A

B

C

Discover more resources for Computers