Project Management with Microsoft projects

Quiz
•
Computers
•
University
•
Medium
Daneillia Burke
Used 2+ times
FREE Resource
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
Question 1: 2 truths one Lie. Find the incorrect phrase.
Microsoft Project allows you to create task dependencies like Finish-to-Start and Start-to-Finish.
Microsoft Project automatically generates Gantt charts without requiring any data input.
You can assign resources such as people, equipment, and materials to tasks in Microsoft Project.
A
B
C
2.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
Question 2: TWO TRUTHS ONE LIE. FIND THE INCORRECT PHRASE
You can set milestones in Microsoft Project by assigning a task with a duration of zero days.
Microsoft Project allows you to track actual task progress by percentage completion.
Microsoft Project automatically adjusts project timelines based on delays without user intervention.
A
B
C
3.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
Question 3: Two truths one lie. Find the incorrect phrase
You can assign deadlines to tasks to ensure they are completed by a specific date in Microsoft Project.
Microsoft Project only supports one view of the project at a time.
Task dependencies in Microsoft Project can be set to different types such as Finish-to-Start and Start-to-Start.
A
B
C
4.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
Question 4:
A) You can update a task's status by entering the percentage of completion in the "Percentage Complete" field in Microsoft Project.
B) The Gantt Chart view in Microsoft Project shows tasks, dependencies, and overall project progress visually.
c) In Microsoft Project, once a project is started, you cannot modify the task durations or start dates.
A
B
C
5.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
Question 5: two truths one lie. Find the incorrect statement
A)Microsoft Project allows you to create task dependencies to determine the order in which tasks must be completed.
B)You can track resource utilization, such as how much work a resource has completed, in Microsoft Project.
C)Microsoft Project only allows tracking of tasks, not resources.
A
B
C
6.
MULTIPLE CHOICE QUESTION
45 sec • 20 pts
QUESTION 6: two truths one lie find the incorrect statement
A) Microsoft Project allows you to print reports such as progress reports and resource allocation reports.
B) You can set up project deadlines directly in the Gantt chart view.
C) Task information, including dates and resources, cannot be modified once entered in Microsoft Project.
A
B
C
Similar Resources on Wayground
8 questions
Application Development (Set 1)

Quiz
•
University
10 questions
MS Project (Task & Pred)

Quiz
•
University
10 questions
Node.js and Express.js Fun Challenge

Quiz
•
University
8 questions
Webtech - tut8 fetch(), NPM und Vite

Quiz
•
University
10 questions
Mastering Microsoft 365 Applications

Quiz
•
12th Grade - University
11 questions
MapReduce Basics

Quiz
•
University
10 questions
Quiz Chap 7

Quiz
•
University
10 questions
Managing Devices

Quiz
•
9th Grade - University
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade