SBEQ2523 Variation

SBEQ2523 Variation

University

15 Qs

quiz-placeholder

Similar activities

Construction Technology

Construction Technology

University

20 Qs

L: SET 0

L: SET 0

University - Professional Development

10 Qs

Project Delivery

Project Delivery

University

18 Qs

Set 1

Set 1

University

20 Qs

Prelim, Prime Cost, Prov Sum and Pro Rata

Prelim, Prime Cost, Prov Sum and Pro Rata

9th Grade - University

10 Qs

SBEQ2523 Payment & Certificates

SBEQ2523 Payment & Certificates

University

15 Qs

Famous Architects and their work

Famous Architects and their work

8th Grade - Professional Development

20 Qs

Refresher 2022

Refresher 2022

University

15 Qs

SBEQ2523 Variation

SBEQ2523 Variation

Assessment

Quiz

Architecture

University

Medium

Created by

FARRAH A

Used 6+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'variation' commonly refer to in construction contracts?

A breach of contract

A change to the originally agreed works

A penalty for delay

A new contract agreement

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT typically a reason for a variation?

Changes in employer requirements

Review of design

Payment delays

Statutory changes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to PAM 2018, which clause defines variation?

Clause 11.0

Clause 24.0

Clause 1.1

Clause 10.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is typically empowered to issue a variation under PAM 2018?

Contractor

Employer

Architect

Quantity Surveyor

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which clause ensures that variations do not vitiate the contract?

Clause 11.1

Clause 11.2

Clause 11.4

Clause 24.3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must accompany the notification of a variation claim under Clause 11.7(a)?

Site photographs

Verbal approval

Preliminary estimate and calculations

Copy of contract

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the deadline for submitting a notice of additional expense due to variation?

14 days

21 days

28 days

60 days

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?