
SBEQ2523 Variation
Authored by FARRAH A
Architecture
University
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the term 'variation' commonly refer to in construction contracts?
A breach of contract
A change to the originally agreed works
A penalty for delay
A new contract agreement
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT typically a reason for a variation?
Changes in employer requirements
Review of design
Payment delays
Statutory changes
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to PAM 2018, which clause defines variation?
Clause 11.0
Clause 24.0
Clause 1.1
Clause 10.3
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is typically empowered to issue a variation under PAM 2018?
Contractor
Employer
Architect
Quantity Surveyor
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which clause ensures that variations do not vitiate the contract?
Clause 11.1
Clause 11.2
Clause 11.4
Clause 24.3
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must accompany the notification of a variation claim under Clause 11.7(a)?
Site photographs
Verbal approval
Preliminary estimate and calculations
Copy of contract
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the deadline for submitting a notice of additional expense due to variation?
14 days
21 days
28 days
60 days
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?