SBEQ2523 Variation

SBEQ2523 Variation

University

15 Qs

quiz-placeholder

Similar activities

Research Methodology Part 2

Research Methodology Part 2

University

10 Qs

RC Stairs

RC Stairs

University

10 Qs

BRICKLAYERS HAND TOOLS

BRICKLAYERS HAND TOOLS

12th Grade - Professional Development

10 Qs

Plate Motion Mid-Unit Assessment

Plate Motion Mid-Unit Assessment

7th Grade - University

16 Qs

Quiz II - History and Theory of Architecture

Quiz II - History and Theory of Architecture

University

11 Qs

Lighting Design Set 2

Lighting Design Set 2

University

10 Qs

Noise Control & Acoustic Design

Noise Control & Acoustic Design

University

17 Qs

TROPICAL DESIGN PRELIM EXAM ARCH2A

TROPICAL DESIGN PRELIM EXAM ARCH2A

University

20 Qs

SBEQ2523 Variation

SBEQ2523 Variation

Assessment

Quiz

Architecture

University

Practice Problem

Medium

Created by

FARRAH A

Used 6+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'variation' commonly refer to in construction contracts?

A breach of contract

A change to the originally agreed works

A penalty for delay

A new contract agreement

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT typically a reason for a variation?

Changes in employer requirements

Review of design

Payment delays

Statutory changes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to PAM 2018, which clause defines variation?

Clause 11.0

Clause 24.0

Clause 1.1

Clause 10.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is typically empowered to issue a variation under PAM 2018?

Contractor

Employer

Architect

Quantity Surveyor

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which clause ensures that variations do not vitiate the contract?

Clause 11.1

Clause 11.2

Clause 11.4

Clause 24.3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must accompany the notification of a variation claim under Clause 11.7(a)?

Site photographs

Verbal approval

Preliminary estimate and calculations

Copy of contract

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the deadline for submitting a notice of additional expense due to variation?

14 days

21 days

28 days

60 days

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?