Project Management MCQs
Authored by TAN VINCY
Engineering
University
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
What is the first phase of the project life cycle?
Planning
Initiation
Execution
Closure
2.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
The document that formally authorizes the existence of a project is called:
Project Scope
Project Plan
Project Charter
Risk Register
3.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
Which of the following is NOT part of the triple constraint?
Cost
Time
Resources
Scope
4.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
The technique used to determine the longest path through a project is:
Gantt Chart
CPM
PERT
SWOT
5.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
What does a Gantt chart primarily show?
Quality of tasks
Task duration and schedule
Budget allocation
Team roles
6.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
In which phase is the Work Breakdown Structure (WBS) created?
Initiation
Planning
Execution
Monitoring
7.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
Which project management methodology emphasizes iterative development?
Waterfall
Agile
Six Sigma
PRINCE2
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?