Project Management MCQs

Authored by TAN VINCY

Engineering

University

Used 3+ times

Project Management MCQs
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

What is the first phase of the project life cycle?

Planning

Initiation

Execution

Closure

2.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

The document that formally authorizes the existence of a project is called:

Project Scope

Project Plan

Project Charter

Risk Register

3.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

Which of the following is NOT part of the triple constraint?

Cost

Time

Resources

Scope

4.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

The technique used to determine the longest path through a project is:

Gantt Chart

CPM

PERT

SWOT

5.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

What does a Gantt chart primarily show?

Quality of tasks

Task duration and schedule

Budget allocation

Team roles

6.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

In which phase is the Work Breakdown Structure (WBS) created?

Initiation

Planning

Execution

Monitoring

7.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

Which project management methodology emphasizes iterative development?

Waterfall

Agile

Six Sigma

PRINCE2

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?