1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Jawzjan province, the project team meets to combine all the individual management plans (scope, schedule, cost, quality, communications, etc.) into one integrated plan before execution begins. What is the team doing in this phase?

Creating individual deliverables for stakeholders

Developing the baselines for measuring project performance

Integrating subsidiary plans into a comprehensive Project Management Plan

Closing all vendor contracts

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Badghis province, the project manager leads the team in setting the initial scope, schedule, and cost baselines that will be used later to track and measure project performance. What specific output is being produced during this phase?

Issue Log

Change Requests

Project Baselines (scope, schedule, cost)

Team Performance Assessments

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Paktia province, the team finalizes a document that outlines how the project will be executed, monitored, controlled, and closed. What process is responsible for producing this document?

Manage Communications

Perform Integrated Change Control

Develop Project Management Plan

Plan Stakeholder Engagement

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Balkh province, the team decides on a formal method for evaluating change requests and ensuring that all changes are properly reviewed before approval. Which activity is happening during the development of the Project Management Plan?

Defining the integrated change control process

Assigning daily operational tasks

Writing the team’s daily reports

Organizing stakeholder satisfaction surveys

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Cairo city in Egypt, while working on project initiation, the team documents guidelines about how scope, cost, quality, risks, and communications will be managed across the project life cycle. What outcome is being achieved?

Drafting the Procurement Agreements

Establishing Management Strategies for Key Knowledge Areas

Closing the Phase Deliverables

Monitoring and Controlling Work Performance

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development