Preventive and Corrective Actions - Assignment

Preventive and Corrective Actions - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

SG20_Test_S3_Ch4_Integration

SG20_Test_S3_Ch4_Integration

Professional Development

10 Qs

Project Charter - Assignment

Project Charter - Assignment

Professional Development

5 Qs

Governance _Culture - Assignment

Governance _Culture - Assignment

Professional Development

6 Qs

Stakeholder Engagement Strategies - Assignment

Stakeholder Engagement Strategies - Assignment

Professional Development

7 Qs

Procurement 10 soal (Chapter 12)

Procurement 10 soal (Chapter 12)

Professional Development

10 Qs

Quiz Lesson 3 - Topic D (Resources and Procurement)

Quiz Lesson 3 - Topic D (Resources and Procurement)

Professional Development

10 Qs

IT PM Career Accelerator Week 2

IT PM Career Accelerator Week 2

Professional Development

10 Qs

Validate and Control Scope - Assignment

Validate and Control Scope - Assignment

Professional Development

6 Qs

Preventive and Corrective Actions - Assignment

Preventive and Corrective Actions - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Nuristan province, the project team completes all project work and ensures that the customer signs off on the final deliverables. What process are they performing?

Validate Scope

Close Project or Phase

Control Quality

Perform Integrated Change Control

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Farah province, the project manager makes sure that all contracts are completed and financial accounts are finalized before officially closing the project. What best describes this activity?

Managing Procurement Activities

Settling Procurement and Financial Closure

Closing Contract Payments Early

Planning Risk Management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Samangan province, after finalizing project work, the team organizes documents like reports, approvals, and lessons learned for archiving. What are they updating?

Issue Log

Organizational Process Assets

Communications Plan

Risk Management Plan

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Buenos Aires city in Argentina, the project manager makes sure team members are officially released from the project and feedback is shared with HR. Which part of project closure is this?

Handing Over Deliverables

Releasing Project Resources

Issuing Final Invoices

Conducting Contract Negotiations

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Wardak province, the sponsor asks for a summary that confirms all objectives were met and that the project is officially complete. Which document will be prepared?

Risk Closure Report

Lessons Learned Document

Project Closure Report

Change Control Summary