Validate and Control Scope - Assignment
Authored by Afghanistan Center
Professional Development
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Khost province, the project sponsor reviews the completed school furniture deliveries against the original scope and signs off on the accepted items. Which process is this?
Control Scope
Validate Scope
Collect Requirements
Review stakeholder satisfaction by using full-cycle alignment, retrospective feedback models, and behavioral consensus metrics
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Herat province, a hospital construction team discovers that the design team added a reception area not originally approved. The project manager takes steps to remove it and align with the scope baseline. What process is being executed?
Define Scope
Control Scope
Validate Scope
Modify work packages through downstream approval forecasting, gap analytics, and multi-party value evaluation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kunduz province, after presenting completed agricultural field tools to local farmers, the sponsor agrees that the deliverables meet the scope and signs the acceptance form. What process does this represent?
Control Scope
Create WBS
Validate Scope
Coordinate stakeholder influence via cross-departmental analysis, value-stream mapping, and consensus-based scoring
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Jowzjan province, the IT project manager compares actual work completed to the scope baseline to ensure no unauthorized features were added during sprint delivery. What process is taking place?
Validate Scope
Monitor Risks
Control Scope
Audit stakeholder alignment with predictive planning thresholds, change freeze periods, and tolerance-based deliverable verification
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Vienna city in Austria, after each sprint, the government platform team demonstrates features to stakeholders and records feedback for formal acceptance. What Scrum-compatible process is being applied?
Validate Scope
Collect Requirements
Control Scope
Perform contract reconciliation using multi-stakeholder matrices and backlog recalibration protocols
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kunar province, a public sanitation project experiences scope creep. The project manager compares deliverables to the original scope plan and raises a change request to remove unapproved work. Which scope-related process is this?
Validate Scope
Control Scope
Plan Scope Management
Apply deviation tracking through layered decision logic, external review cycles, and progressive elaboration reporting
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
11 questions
The Mediately Quiz 🤓🧐
Quiz
•
Professional Development
10 questions
quiz 06.10.2023
Quiz
•
Professional Development
10 questions
ComCon S2 - Laos
Quiz
•
Professional Development
10 questions
Behavioral Test
Quiz
•
Professional Development
10 questions
Complete Recovery EQ DAY 2
Quiz
•
Professional Development
10 questions
INTELLIGENCE
Quiz
•
Professional Development
10 questions
Gujarat State
Quiz
•
KG - Professional Dev...
10 questions
1.6.5 Charging Solutions for MB cars
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade