Validate and Control Scope - Assignment

Validate and Control Scope - Assignment

Professional Development

6 Qs

quiz-placeholder

Similar activities

Practice Exam 2 Part 2

Practice Exam 2 Part 2

Professional Development

10 Qs

BA Review

BA Review

Professional Development

11 Qs

Scope Management Process - Assignment

Scope Management Process - Assignment

Professional Development

7 Qs

Final Quiz - Assignment

Final Quiz - Assignment

Professional Development

10 Qs

Quiz for Become A Project Manager

Quiz for Become A Project Manager

Professional Development

10 Qs

Quizziz 2- Knowledge Area 1 and 2

Quizziz 2- Knowledge Area 1 and 2

Professional Development

10 Qs

IT PM Career Accelerator Week 2

IT PM Career Accelerator Week 2

Professional Development

10 Qs

Governance _Culture - Assignment

Governance _Culture - Assignment

Professional Development

6 Qs

Validate and Control Scope - Assignment

Validate and Control Scope - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Khost province, the project sponsor reviews the completed school furniture deliveries against the original scope and signs off on the accepted items. Which process is this?

Control Scope

Validate Scope

Collect Requirements

Review stakeholder satisfaction by using full-cycle alignment, retrospective feedback models, and behavioral consensus metrics

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Herat province, a hospital construction team discovers that the design team added a reception area not originally approved. The project manager takes steps to remove it and align with the scope baseline. What process is being executed?

Define Scope

Control Scope

Validate Scope

Modify work packages through downstream approval forecasting, gap analytics, and multi-party value evaluation

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kunduz province, after presenting completed agricultural field tools to local farmers, the sponsor agrees that the deliverables meet the scope and signs the acceptance form. What process does this represent?

Control Scope

Create WBS

Validate Scope

Coordinate stakeholder influence via cross-departmental analysis, value-stream mapping, and consensus-based scoring

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Jowzjan province, the IT project manager compares actual work completed to the scope baseline to ensure no unauthorized features were added during sprint delivery. What process is taking place?

Validate Scope

Monitor Risks

Control Scope

Audit stakeholder alignment with predictive planning thresholds, change freeze periods, and tolerance-based deliverable verification

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Vienna city in Austria, after each sprint, the government platform team demonstrates features to stakeholders and records feedback for formal acceptance. What Scrum-compatible process is being applied?

Validate Scope

Collect Requirements

Control Scope

Perform contract reconciliation using multi-stakeholder matrices and backlog recalibration protocols

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kunar province, a public sanitation project experiences scope creep. The project manager compares deliverables to the original scope plan and raises a change request to remove unapproved work. Which scope-related process is this?

Validate Scope

Control Scope

Plan Scope Management

Apply deviation tracking through layered decision logic, external review cycles, and progressive elaboration reporting