1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager uses a conflict resolution technique that is not optimal but often necessary. Each party receives something but must give up something in return. This technique may lead to buyer's remorse. Which of the following techniques is described?

Collaborate/Problem Solve

Compromise/Reconcile

Force/Direct

Withdraw/Avoid

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Ram uses a conflict management technique that incorporates multiple viewpoints and shows a cooperative attitude to solve the conflict. Ram wants to strive for consensus and commitment. Which of the following techniques is Ram using in the scenario?

Withdraw/Avoid

Collaborate/Problem Solve

Force/Direct

Smooth/Accommodate

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

While reviewing various power sources, a project manager notes one power is the ability to gain support when the project team and stakeholders perceive the project manager as possessing special knowledge. Others must also perceive this knowledge as functional expertise that they consider essential. In addition, this power must be earned. What power is under consideration?

Position power

Referent power

Reward power

Expert power

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which role and responsibility would not be a consideration when implementing a predictive project?

Agile Coach

Scrum Master

Product Owner

Kanban Facilitator

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are communicating with a stakeholder with high power and low interest in the project. Which strategy is most appropriate to manage and engage with this customer?

Manage closely

Monitor

Keep informed

Keep satisfied

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following documents can a project manager use to define current and desired stakeholder commitment levels and develop strategies to adjust the commitment levels?

Stakeholder register

Stakeholder Engagement Plan

Team charter

Communications management plan

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager must define and document ground rules and norms to guide the team's behavior. Which tool is best to achieve this goal?

Project chatter

Business case

Team charter

Team norms sheet

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?