30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

The prom committee is having a contest to design the invitation and poster for this year's prom. To ensure getting the design to the printer by the January 15th deadline, the committee is holding the contest in November. This is an example of:

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis estimating.

2.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construction is using:

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis.

3.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:

analogous estimating.

parametric estimating.

reserve analysis estimating.

three-point estimating.

4.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Gwen is leading a Web design project and has determined that the optimistic time for completion is 2 months, the pessimistic time is 12 months, and the likely time for completion is 5 months. Using three-point analysis (TE = (O + 4L + P) รท 6), what is the expected duration for Gwen's project?

2.79 months

3.29 months

5 months

5.67 months

5.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:

analogous estimating.

bottom-up estimating.

reserve analysis.

three-point estimating.

6.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

It took Scott's team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott's duration estimation for this project is an example of:

bottom-up estimating.

parametric estimating.

reserve analysis.

three-point estimating.

7.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?

analogous estimating

parametric estimating

reserve analysis

three-point estimating

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?