24-25 Earn Value Test (complete)

24-25 Earn Value Test (complete)

11th Grade

30 Qs

quiz-placeholder

Similar activities

System Development Life Cycle - 12CompSci

System Development Life Cycle - 12CompSci

10th Grade - University

25 Qs

InDesign q1

InDesign q1

9th - 12th Grade

25 Qs

Photoshop CC 2020 Certification

Photoshop CC 2020 Certification

9th - 12th Grade

33 Qs

Illustrator 1st Vocabulary Test

Illustrator 1st Vocabulary Test

9th - 12th Grade

25 Qs

Illustrator Terms 1 Test

Illustrator Terms 1 Test

9th - 12th Grade

25 Qs

R093 revision

R093 revision

9th - 12th Grade

30 Qs

AI Project Cycle

AI Project Cycle

10th - 11th Grade

25 Qs

Foundations Chapter 9 Exam

Foundations Chapter 9 Exam

9th - 12th Grade

35 Qs

24-25 Earn Value Test (complete)

24-25 Earn Value Test (complete)

Assessment

Quiz

Computers

11th Grade

Easy

Created by

Bobbie Jones

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The prom committee is having a contest to design the invitation and poster for this year's prom. To ensure getting the design to the printer by the January 15th deadline, the committee is holding the contest in November. This is an example of:

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis estimating.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construction is using:

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:

analogous estimating.

parametric estimating.

reserve analysis estimating.

three-point estimating.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Gwen is leading a Web design project and has determined that the optimistic time for completion is 2 months, the pessimistic time is 12 months, and the likely time for completion is 5 months. Using three-point analysis (TE = (O + 4L + P) ÷ 6), what is the expected duration for Gwen's project?

2.79 months

3.29 months

5 months

5.67 months

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:

analogous estimating.

bottom-up estimating.

reserve analysis.

three-point estimating.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It took Scott's team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott's duration estimation for this project is an example of:

bottom-up estimating.

parametric estimating.

reserve analysis.

three-point estimating.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?

analogous estimating

parametric estimating

reserve analysis

three-point estimating

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?