SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

University

15 Qs

quiz-placeholder

Similar activities

Trivia

Trivia

University

20 Qs

Creta y Micenas

Creta y Micenas

University

11 Qs

TRIPLE PYTHAGORAS

TRIPLE PYTHAGORAS

2nd Grade - University

19 Qs

Quiz II - History and Theory of Architecture

Quiz II - History and Theory of Architecture

University

11 Qs

Alatan Lukisan Teknikal

Alatan Lukisan Teknikal

University

20 Qs

Asesment VII

Asesment VII

7th Grade - University

20 Qs

Architectural Lingo (Part 1 of 2)

Architectural Lingo (Part 1 of 2)

University - Professional Development

16 Qs

Kuis seputar Perspektif

Kuis seputar Perspektif

University

10 Qs

SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

Assessment

Quiz

Architecture

University

Hard

Created by

FARRAH A

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Under PAM Contract, the contractor is required to proceed with the works:

A. As slowly as needed

B. Without any planning

C. Regularly and diligently

D. Only when instructed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. 2. What is the main clause in PAM 2006/2018 that governs Extension of Time (EOT)?

A. Clause 11.0

B. Clause 23.0

C. Clause 24.0

D. Clause 21.0

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. Which of the following is NOT a duty of the employer under the contract?

A. Duty of positive cooperation

B. Duty of non-hindrance

C. Duty to supply materials

D. Duty to prevent contractor from completing early

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Delay caused by extreme weather is categorized as:

A. Employer delay

B. Neutral event

C. Contractor’s fault

D. Liquidated damages event

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5. What is the consequence if the architect fails to issue an EOT certificate for employer-caused delay?

A. Contractor must pay LAD

B. Time becomes at large

C. Contractor is penalized

D. Project is terminated

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. Which clause requires the contractor to notify intention to claim EOT?

A. Clause 11.1

B. Clause 23.1(a)

C. Clause 23.3

D. Clause 24.0

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. According to Clause 23.1(b), when must the contractor submit full particulars after the delay ends?

A. Immediately

B. Within 7 days

C. Within 14 days

D. Within 28 days

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?