SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

University

15 Qs

quiz-placeholder

Similar activities

BQS601 INTRODUCTION

BQS601 INTRODUCTION

University

12 Qs

Professional Practice Quiz#3

Professional Practice Quiz#3

University

10 Qs

PP -SPP DOCS ANEX A

PP -SPP DOCS ANEX A

University

20 Qs

Quiz on Quantity Surveying

Quiz on Quantity Surveying

University

10 Qs

Week3_Q1_Time Terms in Construction Project

Week3_Q1_Time Terms in Construction Project

University

15 Qs

Standard of Professional Practice

Standard of Professional Practice

University

10 Qs

L: SET 0

L: SET 0

University - Professional Development

10 Qs

QUIZ FBC 2: introduction to fbc

QUIZ FBC 2: introduction to fbc

University

12 Qs

SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

Assessment

Quiz

Architecture

University

Hard

Created by

FARRAH A

Used 5+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Under PAM Contract, the contractor is required to proceed with the works:

A. As slowly as needed

B. Without any planning

C. Regularly and diligently

D. Only when instructed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. 2. What is the main clause in PAM 2006/2018 that governs Extension of Time (EOT)?

A. Clause 11.0

B. Clause 23.0

C. Clause 24.0

D. Clause 21.0

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. Which of the following is NOT a duty of the employer under the contract?

A. Duty of positive cooperation

B. Duty of non-hindrance

C. Duty to supply materials

D. Duty to prevent contractor from completing early

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Delay caused by extreme weather is categorized as:

A. Employer delay

B. Neutral event

C. Contractor’s fault

D. Liquidated damages event

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5. What is the consequence if the architect fails to issue an EOT certificate for employer-caused delay?

A. Contractor must pay LAD

B. Time becomes at large

C. Contractor is penalized

D. Project is terminated

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. Which clause requires the contractor to notify intention to claim EOT?

A. Clause 11.1

B. Clause 23.1(a)

C. Clause 23.3

D. Clause 24.0

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. According to Clause 23.1(b), when must the contractor submit full particulars after the delay ends?

A. Immediately

B. Within 7 days

C. Within 14 days

D. Within 28 days

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?