PMI PMP - Scope & Stakeholders

PMI PMP - Scope & Stakeholders

Assessment

Quiz

Other

Professional Development

Hard

Created by

Arun Sharma

Used 9+ times

FREE Resource

Student preview

quiz-placeholder

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new project manager has been assigned to a project during its execution stage. During a review of the work breakdown structure (WBS), the project manager discovers that some deliverables were overlooked. The project manager needs to ensure that no work is left out of the project scope and no extra work is performed.

What should the project manager do next?

Add the work to the WBS and recalculate the project metrics.

Ask the stakeholders if these deliverables need to be added to the WBS.

Roll up the lower-level deliverables into higher-level work already accounted for in the WBS

  1. Initiate a Change Control Request with the project management office (PMO).

Answer explanation

A. Add the work to the WBS and recalculate the project metrics

The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team in order to accomplish the project objectives and create the required deliverables. The WBS organizes and defines the total scope of the project and represents the work specified in the currently approved project scope statement. This must always reflect the complete and accurate scope of work.

There is no need to go to the stakeholders as the scope was agreed and not changed.

The WBS needs to reflect the reality without "rolling up" to existing items.

The original scope needs to be delivered, therefore there is no change and no role for the PMO.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Common problems during project scope definition are internal and external dependencies. Which of the following is a dependency that can add complexity to the project?

Non-dependency between a project and the overall program.

Underfunded projects that are dependent upon external resources.

Non-dependency of the project upon an environment in which it is designed to be functional.

  1. Over-staffed project with extra capacity.

Answer explanation

B. Underfunded projects that are dependent upon external resources

More resources than estimated need can be a risk mitigation strategy. It is neither internal or external dependency related to scope.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The sponsor of a hybrid project wants to see a more detailed breakdown in the project charter, not just the milestones. The project manager informs the sponsor that preparing the breakdown will require two more iterations.

Why is this additional time required?

The milestone schedule was prepared based on the project manager's experience only.

The steering committee has to review and approve the schedule first.

Scope in the charter should be approved before detail planning with the team can occur.

Schedule details are only planned one iteration in advance in a hybrid approach.

Answer explanation

C. Scope in the charter should be approved before detail planning with the team can occur.

Project Charter scope needs to be agreed on by the sponsor before the team starts detailed planning.

The other answer choices are incorrect because they are not relevant as the ask is about detail planning and not on a milestone schedule.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During acceptance testing of a deliverable, some senior stakeholders complain that a feature essential to their department was not included. What should the project manager have done to prevent this?

Consulted lessons learned from similar projects to adapt processes

Prepared a change management plan and logged changes during project implementation

Analyzed the project charter and developed a scope management plan

  1. Prepared a prototype and conducted a product demo with stakeholders

Answer explanation

C. Analyzed the project charter and developed a scope management plan

Analyzed the project charter and developed a scope management plan is correct, because the question is about what Project Manager should have done to prevent this situation. The scope management plan is a component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified.

The remaining options are not correct for the reasons explained below

  • Consulted ... appears to be close but it is a distractor because lessons learned provides an insight of how other projects were executed in general

  • Prepared a change.... is the next step but not what should have been done to prevent this situation

  • Prepared a Prototype.... is on the basis of Scope and Requirements which is part of Scope Management plan

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is working on a new software development project and has met with the customer to discuss their requirements. The customer has provided the project manager with a list of requirements, but did not differentiate the technical requirements from the customer requirements.

Which of the following requirements should the project manager classify as a customer requirement?

The software should be able to process 1000 transactions per second.

The software should use a secure database encryption algorithm.

  1. The software should be able to run on a variety of operating systems.

The software should be easy to use and navigate

Answer explanation

D. The software should be easy to use and navigate.

Customer requirements refer to the specifications or features of a product or service deemed necessary by customers that must be completed (developed and tested) for the project to be completed. They are more general and describe what the customer wants the product or service to do. They are typically expressed in the customer's own words and may not be specific enough to be implemented and tested. It is important to note that customer requirements are the starting point for technical requirements. The project team needs to work with the customer to understand their requirements and then translate those requirements into more specific technical requirements that can be implemented.

The other answer choices are incorrect because they are classified as technical requirements. They are specific enough to be implemented and tested. They describe what the software should do, how it should behave, and the desired quality attributes it should have.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While executing a project that is nearly behind schedule, a project manager must commission a new piece of equipment. Two local parties who will be impacted by this commission ask that the project be stopped immediately because they were not given an opportunity to provide project approval.

How would implementing a stakeholder engagement plan have helped the project manager avoid this situation?

By using the conflict management techniques described in the plan, the project manager could have gotten approval from the local parties.

  1. B.Including the local parties in the plan would have ensured their sign-off and approval of the project charter.

By understanding the local parties' expectations, the project manager could have used appropriate negotiating techniques to engage them.

By identifying the local parties as stakeholders, they would have been included in relevant communications.

Answer explanation

D. By identifying the local parties as stakeholders, they would have been included in relevant communications

By identifying the local parties as stakeholders, they would have been included in relevant communications is the correct answer as stakeholder identification should include all parties affected by the project including local, external and internal. The project charter formally authorizes the project,

Conflict management and negotiations are soft skills used after stakeholders are identified

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new project stakeholder is identified who has interest in, but little authority or influence on, the project. How should the project manager handle this stakeholder?

Provide information to the stakeholder as needed.

Work closely with the stakeholder to proactively address their concerns.

Keep track of the stakeholder and respond to their needs.

Include the stakeholder on standard updates and keep them satisfied.

Answer explanation

A. Provide information to the stakeholder as needed

Since the stakeholder has little authority or influence, the project manager does not need to work closely with them to address their concerns, or to keep track of them and their needs. The stakeholder does not need standard updates, either. The project manager should determine the stakeholder's needs and provide information to them to meet their needs.

High power, high-interest stakeholders should be closely managed.

Stakeholders with high power and low interest should be kept satisfied.

Those with low interest and low power shall be only monitored with minimum effort.

A stakeholder with low power and high interest in a project should be kept informed.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?