PMP Exam Simulator - PMP Exam 1

PMP Exam Simulator - PMP Exam 1

Professional Development

5 Qs

quiz-placeholder

Similar activities

HC & OPS Sesi 1

HC & OPS Sesi 1

Professional Development

6 Qs

Construction Site Safety Quiz

Construction Site Safety Quiz

Professional Development

7 Qs

Financial Literacy Quiz

Financial Literacy Quiz

Professional Development

10 Qs

LMS Best Practices Quiz

LMS Best Practices Quiz

Professional Development

10 Qs

Microsoft

Microsoft

Professional Development

10 Qs

PR and

PR and

Professional Development

10 Qs

Post Test Sosialisasi SMT Revisi Tahun 2022 Hari ke-3 (Room 1)

Post Test Sosialisasi SMT Revisi Tahun 2022 Hari ke-3 (Room 1)

Professional Development

9 Qs

PMP Exam Simulator - PMP Exam 1

PMP Exam Simulator - PMP Exam 1

Professional Development

5 Qs

PMP Exam Simulator - PMP Exam 1

PMP Exam Simulator - PMP Exam 1

Assessment

Quiz

others

Professional Development

Medium

Created by

Training eNetwoQ ServIT Indonesia

Used 1+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is still in the process of closing out all past projects. They have obtained final acceptance and transferred ownership of deliverables, ensured that all contracts are closed, and released all project resources. However, project stakeholders have not been informed that the project work has been completed. Finally, the project manager will obtain lessons learned and update organizational process assets. Based on the information provided, what might have been forgotten?

Resolving project requirements

Verifying the final project status

Sharing the final project status

Conducting lessons learned

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What project management process ensures that all documents throughout the project life cycle, as the project manager creates the lessons learned register, will grant the lessons learned register access to the team members?

Direct and Manage Project Work

Monitor and Control Project Work

Manage Project Knowledge

Create Lessons Learned

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project team states they have finished creating the requirements management plan, the requirements traceability matrix, and the requirements documentation. The next step is working on the project work breakdown structure (WBS) result. What is the project team forgetting to do?

Create the project scope statement

Complete the project management plan

Obtain formal acceptance of scope

Perform the validate scope process

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A project manager has developed the following earned value analysis chart for a software development project. Based on the current result, what action should the project manager take?

Submit a change request to increase funding for the project

Look for other projects to which the team members can be reassigned, as the project objectives are not achievable

Determine whether it is feasible to bring the project back to alignment with the project objectives

Question the earned value accuracy

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager and stakeholder are in a heated debate as the stakeholder is requesting a scope change to the project. The project manager has explained that the requested change will impact the project schedule, cost, and risks due to data. The project manager states that the impact analysis results are to be presented to the project manager, and the decision is final. Should the project manager have the prescribed authority to resolve the conflict?

No. The project manager needs to have formal authority to make the final decision.

Yes. The project manager should have the prescribed authority to resolve the conflict.

No. The project manager should not have the prescribed authority to resolve the conflict.

Yes. The project manager should not be compromised with the stakeholder.