Search Header Logo

Quiz 61

Authored by Training eNetwoQ ServIT Indonesia

others

Professional Development

Used 1+ times

Quiz 61
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is still in the process of closing out all past projects. They have obtained final acceptance and transferred ownership of deliverables, ensured that all contracts are closed, and released all project resources. However, project stakeholders have not been informed that the project work has been completed. Finally, the project manager will obtain lessons learned and update organizational process assets. Based on the information provided, what might have been forgotten?

Resolving project requirements

Verifying the final project status

Sharing the final project status

Conducting lessons learned

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What project management process ensures that all documents throughout the project life cycle, as the project manager creates the lessons learned register, will grant the lessons learned register access to the team members?

Direct and Manage Project Work

Monitor and Control Project Work

Manage Project Knowledge

Create Lessons Learned

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project team states they have finished creating the requirements management plan, the requirements traceability matrix, and the requirements documentation. The next step is working on the project work breakdown structure (WBS) result. What is the project team forgetting to do?

Create the project scope statement

Complete the project management plan

Obtain formal acceptance of scope

Perform the validate scope process

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A project manager has developed the following earned value analysis chart for a software development project. Based on the current result, what action should the project manager take?

Submit a change request to increase funding for the project

Look for other projects to which the team members can be reassigned, as the project objectives are not achievable

Determine whether it is feasible to bring the project back to alignment with the project objectives

Question the earned value accuracy

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager and stakeholder are in a heated debate as the stakeholder is requesting a scope change to the project. The project manager has explained that the requested change will impact the project schedule, cost, and risks due to data. The project manager states that the impact analysis results are to be presented to the project manager, and the decision is final. Should the project manager have the prescribed authority to resolve the conflict?

No. The project manager needs to have formal authority to make the final decision.

Yes. The project manager should have the prescribed authority to resolve the conflict.

No. The project manager should not have the prescribed authority to resolve the conflict.

Yes. The project manager should not be compromised with the stakeholder.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?