Critical Path Analysis (CPA) in Project Management Quiz

Critical Path Analysis (CPA) in Project Management Quiz

12th Grade

17 Qs

quiz-placeholder

Similar activities

DM_103 II Animation

DM_103 II Animation

9th - 12th Grade

13 Qs

RDI - Unit 1 Lessons 1-2

RDI - Unit 1 Lessons 1-2

9th - 12th Grade

15 Qs

Topic 4.6 Robots in automation

Topic 4.6 Robots in automation

11th - 12th Grade

13 Qs

Scales of Production

Scales of Production

10th - 12th Grade

20 Qs

Certification Prep Unit  One

Certification Prep Unit One

9th - 12th Grade

14 Qs

WEB DESIGN AND PRINCPLE

WEB DESIGN AND PRINCPLE

11th Grade - University

20 Qs

Adobe Indesign Certification Practice Two - 2023

Adobe Indesign Certification Practice Two - 2023

9th - 12th Grade

20 Qs

Adobe Illustrator

Adobe Illustrator

9th - 12th Grade

22 Qs

Critical Path Analysis (CPA) in Project Management Quiz

Critical Path Analysis (CPA) in Project Management Quiz

Assessment

Quiz

Design

12th Grade

Medium

Created by

Matthew Greenep

Used 2+ times

FREE Resource

17 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main purpose of Critical Path Analysis (CPA) in project management?

To help plan and schedule complex projects.

To increase the number of tasks in a project.

To reduce the number of team members.

To eliminate the need for deadlines.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes a Critical Task in Critical Path Analysis?

A task that must be finished on time to prevent the whole project from being delayed.

A task that can be delayed without affecting the project.

A task that is optional in the project.

A task that is completed first in every project.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Critical Path in a project?

The longest sequence of tasks that must be completed on time to prevent a delay in the project completion.

The shortest sequence of tasks in a project.

The list of tasks that can be delayed.

The path with the least number of tasks.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which step in Critical Path Analysis involves drawing a graphical representation of all tasks and their dependencies?

Network Diagram

Task Identification

Sequencing

Estimate Task Duration

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to calculate the Earliest Start Time (EST) and Latest Finish Time (LFT) for each task in a project?

To identify where delays can be tolerated without affecting the overall project timeline.

To increase the number of tasks in the project.

To reduce the project budget.

To assign more resources to non-critical tasks.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does Critical Path Analysis help project managers?

It allows them to work out the most efficient sequence of events to complete a project.

It helps them avoid creating a project schedule.

It ensures all tasks are completed at the same time.

It eliminates the need for team meetings.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager wants to minimize delays and costs in a project. Which tool should they use according to the material?

Critical Path Analysis (CPA)

Brainstorming

SWOT Analysis

Market Research

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?