D30 QUIZ OF THE DAY

D30 QUIZ OF THE DAY

University

25 Qs

quiz-placeholder

Similar activities

D27 CHECK YOUR LEVEL

D27 CHECK YOUR LEVEL

University

25 Qs

Investment Financial Accounting II

Investment Financial Accounting II

10th Grade - University

20 Qs

QUIZ 1 : TOPIC 4 [COST VOLUME PROFIT ANALYSIS]

QUIZ 1 : TOPIC 4 [COST VOLUME PROFIT ANALYSIS]

1st Grade - University

20 Qs

QUIZ 1 : TOPIC 8 [JOB ORDER COSTING]

QUIZ 1 : TOPIC 8 [JOB ORDER COSTING]

1st Grade - University

20 Qs

1- UBUNTU GESTIÓ USUARIS

1- UBUNTU GESTIÓ USUARIS

University

20 Qs

QUIZ 3 : TOPIC 2 [MANUFACTURING COSTS:CONCEPTS & COMPONENTS]

QUIZ 3 : TOPIC 2 [MANUFACTURING COSTS:CONCEPTS & COMPONENTS]

1st Grade - University

20 Qs

Ebus2Guadeloupe22-23Businessplan01

Ebus2Guadeloupe22-23Businessplan01

University

20 Qs

VM Mid Sem Quiz 202020211

VM Mid Sem Quiz 202020211

University

20 Qs

D30 QUIZ OF THE DAY

D30 QUIZ OF THE DAY

Assessment

Quiz

Professional Development

University

Easy

Created by

WINCENTRE CLASSES

Used 2+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the volume of one bag of cement?
0.05 m³
0.035 m³
0.045 m³
0.030 m³

Answer explanation

The volume of one 50 kg bag of cement is 0.035 m³ or 35 liters.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the percentage of contractor’s profit considered in estimation?
5%
7%
10%
12%

Answer explanation

A standard 10% of the estimated cost is considered as contractor's profit.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In estimation, centage charges are also known as:
Overhead charges
Lump sum provision
Supervision charges
Material wastage

Answer explanation

Centage charges are also known as supervision charges, included for works carried out by another department.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which estimate is made when additional works are added to the original project?
Revised Estimate
Supplementary Estimate
Abstract Estimate
Detailed Estimate

Answer explanation

Supplementary Estimate is prepared for any new or additional works related to the original project.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of 'Tools and Plant' provision in estimate?
For buying machinery and software
For material testing
For purchasing required construction tools
For building supervision

Answer explanation

T&P refers to provision for purchasing tools and plant used in execution of work.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the percentage provided for electrification and water supply in building estimates?
5%
10%
15%
20%

Answer explanation

20% of the building estimate is provided for electrification, sanitary and water supply.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which sanction confirms technical soundness and design feasibility?
Administrative Sanction
Expenditure Sanction
Technical Sanction
Project Approval

Answer explanation

Technical sanction confirms that the project design and detailed estimate are sound and executable.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?