1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the volume of one bag of cement?

0.05 m³
0.035 m³
0.045 m³
0.030 m³

Answer explanation

The volume of one 50 kg bag of cement is 0.035 m³ or 35 liters.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the percentage of contractor’s profit considered in estimation?

5%
7%
10%
12%

Answer explanation

A standard 10% of the estimated cost is considered as contractor's profit.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In estimation, centage charges are also known as:

Overhead charges
Lump sum provision
Supervision charges
Material wastage

Answer explanation

Centage charges are also known as supervision charges, included for works carried out by another department.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which estimate is made when additional works are added to the original project?

Revised Estimate
Supplementary Estimate
Abstract Estimate
Detailed Estimate

Answer explanation

Supplementary Estimate is prepared for any new or additional works related to the original project.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of 'Tools and Plant' provision in estimate?

For buying machinery and software
For material testing
For purchasing required construction tools
For building supervision

Answer explanation

T&P refers to provision for purchasing tools and plant used in execution of work.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the percentage provided for electrification and water supply in building estimates?

5%
10%
15%
20%

Answer explanation

20% of the building estimate is provided for electrification, sanitary and water supply.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which sanction confirms technical soundness and design feasibility?

Administrative Sanction
Expenditure Sanction
Technical Sanction
Project Approval

Answer explanation

Technical sanction confirms that the project design and detailed estimate are sound and executable.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?