
Change Control Process - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team receives a client request to add an extra feature during execution. What should the project manager do first?
Implement the change immediately to keep the client happy
Assess the impact on cost, time, and quality
Reject the change since the project is already in execution
Add the change to the deliverables list
Answer explanation
The change control process requires evaluating the impact of a change before any action. It ensures that decisions are informed and aligned with project objectives.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a weekly meeting, a stakeholder verbally requests a change to the project scope. What should the project manager do next?
Accept the request and inform the team
Tell the stakeholder to wait until project completion
Ask the stakeholder to submit a formal change request
Modify the scope baseline immediately
Answer explanation
All change requests must be documented. Without formal submission, the change cannot enter the change control process.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A change request has been submitted and evaluated. What is the next step in the integrated change control process?
Update the risk register
Submit the change to the Change Control Board (CCB)
Communicate the change to all stakeholders
Answer explanation
After impact analysis, the CCB is responsible for reviewing and making decisions on change requests.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A change request was rejected by the Change Control Board. What should the project manager do next?
Inform stakeholders and revise the project baseline
Remove the change from all records
Update the change log and notify the initiator
Implement the change regardless
Answer explanation
Even rejected changes must be logged. The initiator needs to be informed to maintain transparency and documentation integrity.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which document is updated once a change is approved?
Project charter
Issue log
Stakeholder register
Project management plan
Answer explanation
Approved changes often require updates to the plan to reflect new baselines, activities, or scope.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary role of the Change Control Board (CCB)?
Implement project changes
Develop the scope baseline
Approve, reject, or defer change requests
Update the stakeholder engagement plan
Answer explanation
The CCB is a formal authority in the change control process that ensures consistent decision-making for proposed changes.
Similar Resources on Wayground
10 questions
EDGE Phase II GC - Recap Quiz

Quiz
•
Professional Development
10 questions
WT for AOII

Quiz
•
Professional Development
10 questions
Communication 10 soal (Chapter 10)

Quiz
•
Professional Development
10 questions
Quiziz Week 2 Day 1

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
6 questions
Validate and Control Scope - Assignment

Quiz
•
Professional Development
10 questions
WT for PDOI

Quiz
•
Professional Development
10 questions
FCBA Exams 1

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade