Change Control Process - Assignment

Authored by Afghanistan Center

Professional Development

Professional Development

Change Control Process - Assignment
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team receives a client request to add an extra feature during execution. What should the project manager do first?

Implement the change immediately to keep the client happy

Assess the impact on cost, time, and quality

Reject the change since the project is already in execution

Add the change to the deliverables list

Answer explanation

The change control process requires evaluating the impact of a change before any action. It ensures that decisions are informed and aligned with project objectives.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a weekly meeting, a stakeholder verbally requests a change to the project scope. What should the project manager do next?

Accept the request and inform the team

Tell the stakeholder to wait until project completion

Ask the stakeholder to submit a formal change request

Modify the scope baseline immediately

Answer explanation

All change requests must be documented. Without formal submission, the change cannot enter the change control process.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A change request has been submitted and evaluated. What is the next step in the integrated change control process?

Update the risk register

Submit the change to the Change Control Board (CCB)

Communicate the change to all stakeholders

Answer explanation

After impact analysis, the CCB is responsible for reviewing and making decisions on change requests.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A change request was rejected by the Change Control Board. What should the project manager do next?

Inform stakeholders and revise the project baseline

Remove the change from all records

Update the change log and notify the initiator

Implement the change regardless

Answer explanation

Even rejected changes must be logged. The initiator needs to be informed to maintain transparency and documentation integrity.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is updated once a change is approved?

Project charter

Issue log

Stakeholder register

Project management plan

Answer explanation

Approved changes often require updates to the plan to reflect new baselines, activities, or scope.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary role of the Change Control Board (CCB)?

Implement project changes

Develop the scope baseline

Approve, reject, or defer change requests

Update the stakeholder engagement plan

Answer explanation

The CCB is a formal authority in the change control process that ensures consistent decision-making for proposed changes.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development