Change Control Process - Assignment

Change Control Process - Assignment

Professional Development

6 Qs

quiz-placeholder

Similar activities

Learnathon S4 - Quiz 1

Learnathon S4 - Quiz 1

Professional Development

10 Qs

Practice Exam 2 Part 1

Practice Exam 2 Part 1

Professional Development

11 Qs

Pre-Test Hubungan Kelembagaan PKA Akt VIII Rohil 2022

Pre-Test Hubungan Kelembagaan PKA Akt VIII Rohil 2022

Professional Development

10 Qs

Stakeholder Management - Assignment

Stakeholder Management - Assignment

Professional Development

7 Qs

Review on Project Management Concepts

Review on Project Management Concepts

Professional Development

10 Qs

Quiz Lesson 4 - Topic E (Communicate and Collaborate with Stakeh

Quiz Lesson 4 - Topic E (Communicate and Collaborate with Stakeh

Professional Development

7 Qs

Project Management quiz

Project Management quiz

Professional Development

8 Qs

LSC Review Modules

LSC Review Modules

Professional Development

10 Qs

Change Control Process - Assignment

Change Control Process - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team receives a client request to add an extra feature during execution. What should the project manager do first?

Implement the change immediately to keep the client happy

Assess the impact on cost, time, and quality

Reject the change since the project is already in execution

Add the change to the deliverables list

Answer explanation

The change control process requires evaluating the impact of a change before any action. It ensures that decisions are informed and aligned with project objectives.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a weekly meeting, a stakeholder verbally requests a change to the project scope. What should the project manager do next?

Accept the request and inform the team

Tell the stakeholder to wait until project completion

Ask the stakeholder to submit a formal change request

Modify the scope baseline immediately

Answer explanation

All change requests must be documented. Without formal submission, the change cannot enter the change control process.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A change request has been submitted and evaluated. What is the next step in the integrated change control process?

Update the risk register

Submit the change to the Change Control Board (CCB)

Communicate the change to all stakeholders

Answer explanation

After impact analysis, the CCB is responsible for reviewing and making decisions on change requests.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A change request was rejected by the Change Control Board. What should the project manager do next?

Inform stakeholders and revise the project baseline

Remove the change from all records

Update the change log and notify the initiator

Implement the change regardless

Answer explanation

Even rejected changes must be logged. The initiator needs to be informed to maintain transparency and documentation integrity.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is updated once a change is approved?

Project charter

Issue log

Stakeholder register

Project management plan

Answer explanation

Approved changes often require updates to the plan to reflect new baselines, activities, or scope.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary role of the Change Control Board (CCB)?

Implement project changes

Develop the scope baseline

Approve, reject, or defer change requests

Update the stakeholder engagement plan

Answer explanation

The CCB is a formal authority in the change control process that ensures consistent decision-making for proposed changes.