
Earned Value Management (EVM) - Assignment
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Hard
Afghanistan Center
FREE Resource
Enhance your content in a minute
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the Cost Performance Index (CPI) indicate in Earned Value Management?
Schedule deviation from the plan
The cost of completing the remaining work
Cost efficiency of the work performed
The time needed to complete the project
Answer explanation
CPI = EV ÷ AC and shows how efficiently the budget is being used. A CPI of 1 means on budget; greater than 1 means under budget; less than 1 means over budget.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the correct formula for Schedule Variance (SV)?
SV = AC - PV
SV = EV - PV
SV = EV - AC
SV = PV - EV
Answer explanation
Schedule Variance indicates how much ahead or behind schedule the project is. It compares earned value to planned value.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your project has the following values:
Planned Value (PV) = $200,000
Earned Value (EV) = $180,000
Actual Cost (AC) = $190,000
What is the Schedule Performance Index (SPI)?
0.95
1.05
0.90
1.10
Answer explanation
SPI = EV ÷ PV = 180,000 ÷ 200,000 = 0.90. This means the project is progressing at 90% of the planned schedule.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You’re tracking the performance of a construction project. The EV is $250,000 and the AC is $275,000. What does the Cost Variance (CV) tell you?
The project is ahead of budget
The project is under budget
The project is on budget
The project is over budget
Answer explanation
CV = EV - AC = $250,000 - $275,000 = -$25,000. A negative value indicates a cost overrun.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a To-Complete Performance Index (TCPI) greater than 1.0 indicate?
The project is performing ahead of schedule
The remaining work must be performed more efficiently than planned
The project is under budget
No additional performance improvement is required
Answer explanation
A TCPI > 1 indicates the project must improve cost efficiency to meet the budget.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working on a bridge construction project. You find the following:
BAC = $500,000
EV = $300,000
AC = $350,000
What is the CPI, and what does it mean?
1.17; project is under budget
0.86; project is over budget
1.17; project is over budget
0.86; project is under budget
Answer explanation
CPI = EV ÷ AC = $300,000 ÷ $350,000 = 0.86. Since CPI < 1, the project is over budget.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which EVM term represents the budgeted cost of work scheduled to be done?
Earned Value (EV)
Actual Cost (AC)
Planned Value (PV)
Schedule Performance Index (SPI)
Answer explanation
PV is the budgeted amount for the work planned to be done up to a specific point in time.
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are evaluating two projects. Project A has a CPI of 1.10, and Project B has a CPI of 0.95.
Which statement is correct?
Project A is over budget
Project B is under budget
Project A is more cost-efficient than Project B
Both projects are equally efficient
Answer explanation
A CPI greater than 1 indicates better cost efficiency. Therefore, Project A is performing more efficiently than Project B.
Similar Resources on Wayground
10 questions
Business Networking Care 3 Topic 3.1
Quiz
•
Professional Development
10 questions
AXIE 101
Quiz
•
KG - Professional Dev...
10 questions
Prof Ed 6
Quiz
•
Professional Development
10 questions
ESL Vocabulary: Technology 1
Quiz
•
University - Professi...
10 questions
INTO Artificial Intelligence
Quiz
•
University - Professi...
11 questions
Term 1 Reflection
Quiz
•
KG - Professional Dev...
12 questions
Communication and Sales by Vishal Jaiswal
Quiz
•
KG - Professional Dev...
10 questions
Linespersons Responsibilities Quiz: Icing
Quiz
•
Professional Development
Popular Resources on Wayground
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
15 questions
Solving Equations with Variables on Both Sides Review
Quiz
•
8th Grade
