Search Header Logo

Earned Value Management (EVM) - Assignment

Authored by Afghanistan Center

Professional Development

Professional Development

Earned Value Management (EVM) - Assignment
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Cost Performance Index (CPI) indicate in Earned Value Management?

Schedule deviation from the plan

The cost of completing the remaining work

Cost efficiency of the work performed

The time needed to complete the project

Answer explanation

CPI = EV ÷ AC and shows how efficiently the budget is being used. A CPI of 1 means on budget; greater than 1 means under budget; less than 1 means over budget.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the correct formula for Schedule Variance (SV)?

SV = AC - PV

SV = EV - PV

SV = EV - AC

SV = PV - EV

Answer explanation

Schedule Variance indicates how much ahead or behind schedule the project is. It compares earned value to planned value.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your project has the following values:

  • Planned Value (PV) = $200,000

  • Earned Value (EV) = $180,000

  • Actual Cost (AC) = $190,000

What is the Schedule Performance Index (SPI)?

0.95

1.05

0.90

1.10

Answer explanation

SPI = EV ÷ PV = 180,000 ÷ 200,000 = 0.90. This means the project is progressing at 90% of the planned schedule.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You’re tracking the performance of a construction project. The EV is $250,000 and the AC is $275,000. What does the Cost Variance (CV) tell you?

The project is ahead of budget

The project is under budget

The project is on budget

The project is over budget

Answer explanation

CV = EV - AC = $250,000 - $275,000 = -$25,000. A negative value indicates a cost overrun.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a To-Complete Performance Index (TCPI) greater than 1.0 indicate?

The project is performing ahead of schedule

The remaining work must be performed more efficiently than planned

The project is under budget

No additional performance improvement is required

Answer explanation

A TCPI > 1 indicates the project must improve cost efficiency to meet the budget.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working on a bridge construction project. You find the following:

  • BAC = $500,000

  • EV = $300,000

  • AC = $350,000
    What is the CPI, and what does it mean?

1.17; project is under budget

0.86; project is over budget

1.17; project is over budget

0.86; project is under budget

Answer explanation

CPI = EV ÷ AC = $300,000 ÷ $350,000 = 0.86. Since CPI < 1, the project is over budget.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which EVM term represents the budgeted cost of work scheduled to be done?

Earned Value (EV)

Actual Cost (AC)

Planned Value (PV)

Schedule Performance Index (SPI)

Answer explanation

PV is the budgeted amount for the work planned to be done up to a specific point in time.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development